Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

An Infor LX upgrade in a month? Crossroads consultants make it happen!

An Infor LX upgrade in a month? Crossroads consultants make it happen!

In August, BISCO, Inc. based in IL went live on their new IBMi 9 with Infor LX. This project included a dual migration from IBMi 7 to IBMi 9 and an upgrade from LX 8.3.4 to LX 8.3.5 using webtop. The Crossroads team led by Tim Baker, made this all happen in just a little over a month. BISCO will immediately move into the next phase of the project which will focus on an implementation of the Avalara Tax Interface to LX.

As stated by BISCO’s Senior Manager of Information Technology, “I want to express our complete gratitude for what a great job Crossroads RMC did in helping us get our BPCS LX Upgrade up and running. We were struggling to get over that hump and just couldn’t seem to bring this ERP to life… Crossroads RMC came in and saved the day, a fantastic job and the effort put forth was 2nd to none. Big Shout out to Tim Baker!!  I would highly recommend Crossroads RMC to any company.

BISCO is an ISO 13485 certified manufacturer of medical devices for the dental industry, specializing in adhesive and resin composite technology. Established in 1981, BISCO is an industry leader providing technically innovative aesthetic and restorative products to dental customers in the U.S. and in over 60 countries worldwide.

Learn more about Crossroads RMC Services>

Previous Article Infor LX & BPCS Tip of the Week: WebTop
Next Article Infor LN & Baan Tip of the Week: Wrap Toolbar Option
Print
22971 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

Advanced Remittance Processing, ARP, provides an automated approach to your cash application process. ARP works together with Accounts Receivable to save valuable time and resources by automatically applying incoming payments to open receivables during daily batch processing. You can easily and efficiently resolve unapplied remittances online.

Advanced Remittance Processing (ARP) is an automatic cash application process that allows you to perform the following functions:

12345679Last

Theme picker

Tips: LN | Baan

A cash flow statement provides a historical view of the movement of cash within a company. This statement offers an overview of both the origins and destinations of cash, aiding management in evaluating the company's ability to fulfill short-term financial obligations. To differentiate between various sources and uses of cash, reason codes can be utilized. When interacting with cash transactions in relevant sessions, users have the option to input or review the corresponding cash flow reason. The cash flow statement organizes cash transactions based on these reasons. LN software system maintains year-specific opening balances for cash flow transactions. Should the need arise, users can manually input opening balances in the Opening Balance Cash Flow (tfgld2118m000) session.

To set up the cash flow statement, use the following sequence of sessions:...

When there are two Cost Items, one with Release to Warehousing applied and the other with Release to Warehousing not applied, upon approval of the Sales Order, the Cost Item that is released to Warehousing will go straight to Staged status, pending Shipment confirmation, while the Cost Item that is not released to Warehousing will be up for Sales Deliveries.

Apart from this main difference in functionality between having and not having this option to release to Warehousing checked, there are other impacts to consider...