Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned

Kathy Barthelt 0 189 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is...

What are your production orders telling you?

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 136 Article rating: 5.0

MEASURE WHAT YOU WANT TO IMPROVE!

Six simple words, but put together they convey a powerful concept that can transform manufacturing companies. It’s a basic concept that’s hard to argue with: Collect data, see where the data leads you, and make changes that have a positive impact on the data. Repeat often.

If your company is manufacturing a product, you’re...

LX User Group Event: Infor Partner Spotlight | Crossroads RMC

Tuesday, May 10 | 12:00pm - 1:00pm ET

Crossroads RMC 0 108 Article rating: 5.0

LX User Group Event

Tuesday, May 10 | 12:00pm - 1:00pm ET
Infor Partner Spotlight | Crossroads RMC

Come hear recent success stories with Crossroads RMC's software MES Ultimate, Analytics Dashboard, and Avalara's interface, along with consulting services that focus on a joint upgrade and MES project with Infor.

Register now →

Mitigating Risk With Your Infor ERP

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 281 Article rating: 5.0

MARCH… "in like a lion and out like a lamb"

Problems = Risk

Boy, it sure seems like we’ve seen our fair share of March “LIONS” over the past few years, wouldn’t you agree? Those lions have manifested mostly as external global problems outside of the control of any given person or manufacturing operation. As we know, problems = risk.

So, how do businesses respond to risk, specifically when it comes to their ERP system? We all deal with risks in our jobs every day. It is our response to the risk that makes all the difference. Creating short-term, midterm, and long-term response strategies ensure that a company can not only handle a fast-changing situation or emergency but also make the investments needed to seize opportunities and become more resilient.

To create these response strategies, manufacturers should examine:

  • How did we get here?
  • Where are we now?
  • Where are we headed?
  • What to do about it?

In order to really dig into each of these areas, our customers have successfully partnered with us to review a particular part of their business that they feel is at risk and sometimes have asked us to review everything…soup to nuts. This review is done through an ERP Utilization Review. In this review, we can dig into such things as...

3+ Reasons to Invest in Automated Tax Compliance with Crossroads RMC & Avalara

Crossroads RMC 0 759 Article rating: 5.0

Without automation, your tax professionals are buried in endless tasks that should be offloaded. Every hour spent on tax management is an hour lost on other, more important, parts of your business. Then, of course, there is the audit risk, UGH!

Crossroads RMC and Avalara provide seamless integrations to Infor LN (ERP LN), Baan, Infor LX (ERP LX), and BPCS.

Want to learn how automating tax compliance can benefit your company? Click on each success story below to find out how a partnership between your organization, Avalara, and Crossroads RMC can be a HUGE WIN for your business!...

“Sorry, boss. We can’t help you move the business forward.”

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 891 Article rating: 5.0

Imagine saying that to your boss, or the president of your company. What would their response be? Do you think they would say, “It’s ok, we can wait to save a ton of money and move us ahead of the competition... No problem... let me know when you have time to work on it.”  Pretty unlikely. Instead, they will want you to...

It’s mid-January and IT’S GO TIME!

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 810 Article rating: 5.0

The calendar is fresh, the resolutions are made and the opportunities are endless!

So, it is time to dive right in and start tackling your to-do’s?

Right??

...Not just yet!

First, you need to take the time to think about your ERP strategy.

What’s an ERP strategy?

Infor LN & Baan Period End & Fiscal Year End Processing Checklist

Kathy Barthelt 0 2576 Article rating: 5.0

Year-end is always a busy time and it is easy to forget things that must be done in your ERP system to close out the year properly and also set you up for a good start to the following year. Here are some things that you should make sure to add to your to-do checklist:

The year-end close process provides an opportunity to:

_____ Remove discontinued items.

_____ Remove sold purchase receipts.

_____ Remove lot attributes for sold lots.

_____ Update standard cost based on current cost field (for environments without Manufacturing only).

Prepare for Year-End Close

_____ Conduct full physical...

RSS
12345678

Theme picker

Tips:  LX | BPCS | M3

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
1345678910Last

Theme picker

Tips: LN | Baan

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is...
1345678910Last

Theme picker

Categories