Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

An Infor LX upgrade in a month? Crossroads consultants make it happen!

An Infor LX upgrade in a month? Crossroads consultants make it happen!

In August, BISCO, Inc. based in IL went live on their new IBMi 9 with Infor LX. This project included a dual migration from IBMi 7 to IBMi 9 and an upgrade from LX 8.3.4 to LX 8.3.5 using webtop. The Crossroads team led by Tim Baker, made this all happen in just a little over a month. BISCO will immediately move into the next phase of the project which will focus on an implementation of the Avalara Tax Interface to LX.

As stated by BISCO’s Senior Manager of Information Technology, “I want to express our complete gratitude for what a great job Crossroads RMC did in helping us get our BPCS LX Upgrade up and running. We were struggling to get over that hump and just couldn’t seem to bring this ERP to life… Crossroads RMC came in and saved the day, a fantastic job and the effort put forth was 2nd to none. Big Shout out to Tim Baker!!  I would highly recommend Crossroads RMC to any company.

BISCO is an ISO 13485 certified manufacturer of medical devices for the dental industry, specializing in adhesive and resin composite technology. Established in 1981, BISCO is an industry leader providing technically innovative aesthetic and restorative products to dental customers in the U.S. and in over 60 countries worldwide.

Learn more about Crossroads RMC Services>

Previous Article Infor LX & BPCS Tip of the Week: WebTop
Next Article Infor LN & Baan Tip of the Week: Wrap Toolbar Option
Print
22971 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

Advanced Remittance Processing, ARP, provides an automated approach to your cash application process. ARP works together with Accounts Receivable to save valuable time and resources by automatically applying incoming payments to open receivables during daily batch processing. You can easily and efficiently resolve unapplied remittances online.

Advanced Remittance Processing (ARP) is an automatic cash application process that allows you to perform the following functions:

12345678910Last

Theme picker

Tips: LN | Baan

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.