Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 60019 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 44711 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 37132 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 69443 Article rating: 5.0

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 55508 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 56083 Article rating: No rating

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Crossroads MES Version 11 Released

Anthony Etzel 0 38572 Article rating: No rating

Crossroads MES Version 11 was rolled out in March, 2014. Some of the new features include a new GUI interface, improved End of Shift review functions, pre-formatted production label printing, and an electronic shop packet on the factory worker Job In screen.

Crossroads MES Released for Tablet

Anthony Etzel 0 34890 Article rating: 3.7

Crossroads RMC announces that the Crossroads MES solution is now compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

RSS
First157158159160161162163164166

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan Tip: All About Invoicing Methods
Next Article Infor LN & Baan Tip: Why was the session "General Ledger Diagnostics Workbench" built?
Print
7572 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories