BPCS/LX Tip of the Week: How To Capture Re-Work Time (Part 1)

Anthony Etzel 0 43265 Article rating: No rating
In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.

BPCS/LX Tip of the Week: Configuration Management

Anthony Etzel 0 44226 Article rating: No rating

Make to Order? No problem if you use the Configuration Management System. This LX product allows you to define and configure a make to order product during Customer Order Entry. Basically, you have the option to create different products under the same common product item. You will get two completely different common end items that are configured from the same common parent.

The customer orders are planned and turned into shop orders for each end item with all the associated components. With an MES solution in place, the shop order side is easy to schedule and allows you to manage the shop floor.

Baan/LN Tip of the Week: Product Configurator - Part 1

Kathy Barthelt 0 54906 Article rating: No rating
What is it?
The configurator consists of a set of features (questions). The options (answers) to these questions then are used to generate the custom bill of material and routing. These questions may be answered at the time of order entry, prior to order entry (in a project or quote) or after order entry (in the project). The order of the questions need not have any relationship to the bill of materials. The configurator may also calculate the selling price, create a unique “smart” item number, custom description and text. Simple rules are used to interpret the answers.

Who uses the configurator?
Companies whose products have options. The configurator eliminates the need for part numbers for all combinations of options. The configurator ensures that the pricing and bills are correct. The configurator also keeps statistics on the frequency the options are selected.
RSS
First154155156157159161162163Last

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan Tip: All About Invoicing Methods
Next Article Infor LN & Baan Tip: Why was the session "General Ledger Diagnostics Workbench" built?
Print
7977 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories