Infor LN & Baan Tip: Can You Backflush An Item If Estimated Quantity is Zero?

Yes, you can backflush an item with an estimated quantity = 0.00 if you haven't already backflushed the order.

For example, you had an order with one component, you reported the quantity at the operation or order level and ran the backflush. Now you realize you need another component added. In this example, the order has already been backflushed, so if you were to add a second component, run backflushing, nothing would happen.

Backflushing is based on the 'quantity to backflush' in report operations or report orders complete. When the quantity is backflushed, the 'quantity to be backflushed' has been reset to 0.00. With a 0.00 quantity, there is nothing left to backflush so nothing happens. 

In this case, you would have to issue the part through warehousing, just as you would have to do if you had a shortage during the backflushing process. If backflushing hasn't already been attempted, you can backflush a component with zero estimated quantity, after you have reported operations or order complete.

Previous Article Increase Production by 10-20% - It's Simple!
Next Article Infor LX & BPCS Materials Tip: Unique ID Generator / Unique Sequence Number
Print
21068 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

245678910Last

Theme picker

Tips: LN | Baan

Ensuring access to historical logistical and financial transaction information for your employees is crucial. However, before proceeding with archiving or deletion, it's essential to evaluate the necessity of retaining this data. Baan and Infor LN (ERP LN) offer standard archiving sessions within major modules that typically handle a significant volume of historical transactions. These sessions are designed to transfer historical data to an archive company before deleting it from the operational company.

When it comes to archiving sessions, you have three primary options:

Many transactions in all kinds of modules use order numbers or serial numbers. These order numbers are most often automatically generated. In the Number Groups (tcmcs0151m000) session you can define groups of order numbers used for dedicated areas. A Number Group is a group of the first free number series that you can assign to a specific use. All the numbers that Infor LN generates in the number groups that are dedicated to the same purpose are unique.

All the first free numbers are stored in the table tcmcs050.

As many different processes can request a free number from the number groups, we often see delays in the performance, due to locking on the first free number records. This locking issue can have a severe impact on the performance of huge batch-type transactions, but also on the performance perceived by individual users in many areas in LN.