Infor LN & Baan Tip: Can You Backflush An Item If Estimated Quantity is Zero?

Yes, you can backflush an item with an estimated quantity = 0.00 if you haven't already backflushed the order.

For example, you had an order with one component, you reported the quantity at the operation or order level and ran the backflush. Now you realize you need another component added. In this example, the order has already been backflushed, so if you were to add a second component, run backflushing, nothing would happen.

Backflushing is based on the 'quantity to backflush' in report operations or report orders complete. When the quantity is backflushed, the 'quantity to be backflushed' has been reset to 0.00. With a 0.00 quantity, there is nothing left to backflush so nothing happens. 

In this case, you would have to issue the part through warehousing, just as you would have to do if you had a shortage during the backflushing process. If backflushing hasn't already been attempted, you can backflush a component with zero estimated quantity, after you have reported operations or order complete.

Previous Article Increase Production by 10-20% - It's Simple!
Next Article Infor LX & BPCS Materials Tip: Unique ID Generator / Unique Sequence Number
Print
66320 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.