Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses

Infor LX & BPCS Tip: Customer Type

Display Customer Type on Order Header Panel – 8.4. Enhancement

This enhancement displays the Customer Type on the Order Header – Billing panel. The Customer Type can be a pricing or promotion qualifier and may convey other important information about the ordering customer during the Order Entry process.

Programs or areas impacted include:

  • Order Header – Billing (ORD700D9)
Previous Article Infor LX & BPCS: Explore IDF Programs
Next Article Infor LN & Baan Tip: Infor ION
Print
12593 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

There can only be one correction period, and it must be the last period in the period table.

There can only be a correction period for Fiscal periods and not for Reporting or Tax. This period is used for the posting of the Automatic Balancing of Profit and Loss entries as well as any auditor adjusting entries that may be made outside the normal year. This allows you to print a trial balance and financial statements of period 1-12, for example, eliminating any of those adjusting entries.

If you have the Company Parameter (Balancing of Profit & Loss) set to Individual Accounts, then it is critical to have a 13th period to post those entries to. With this setting, the Automatic Balancing will zero out each individual P&L account in the last period. You want this to be period 13 and not period 12.

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

First135136137138140142143144Last

Theme picker

Categories