Baan/LN Tip of the Week: Switching to a Difference Series

Kathy Barthelt 0 204 Article rating: No rating

In general, you can enter a different series in the order field if you have an available series.

To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1). Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

BPCS/LX Tip of the Day: MRP/MPS Simulation

Anthony Etzel 0 786 Article rating: No rating
The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

BPCS/LX Tip of the Day: Inventory Stocking Levels – LX

Anthony Etzel 0 735 Article rating: No rating

The system supports four levels of inventory. You can view summaries of stock at each level through the Material Status Inquiry program or through reports.

 

Below are the four levels:

â–Ş  Item

â–Ş  Item + warehouse

â–Ş  Item + warehouse + location

â–Ş  Item + warehouse + location + lot

 

The lot number level and/or container of inventory can cross multiple warehouses and locations. For example, item + lot or item + lot + container. Locations exist within warehouses. There is no limit on the number of warehouses, locations, or lots that you can assign to an item.

Baan/LN Tip of the Day: Transfers - LN

Kathy Barthelt 0 2779 Article rating: No rating
A Transfer involves either one or two warehouses. If items are transferred between two different warehouses, all activities of the warehousing procedures must be carried out. However, if a transfer takes place between two locations within the same warehouse, the receipt activities are not carried out. You can use transfer orders to define a replenishment system within a single warehouse. This system controls replenishment from bulk locations to pick locations. Note: LN allows you to modify the outbound order line data based on the value the Allow Updating Outbound Order Lines up to and including field is set to in the Warehousing Order Types (whinh0110m000) session.
RSS
First141142143144146148149150Last

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

1345678910Last

Theme picker

Tips: LN | Baan

Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate the cumulative lead time (also called “the Critical Path”) for you.


Infor LN does not differentiate between the two. It is simply Enterprise Planning EP with one set of planned orders. It's possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists in the purchase and manufactured planned items. It has non-critical and critical lead time based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V

Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN

Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Contact us today to learn more:  800.762.2077 | solutions@crossroadsrmc.com

Previous Article Infor ERP Tip: 57% of Companies Have Experienced Some Type of Cyber Attack
Next Article Infor LN & Baan Tip: Company versus Site
Print
13827 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories