Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
9675 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

Advanced Remittance Processing, ARP, provides an automated approach to your cash application process. ARP works together with Accounts Receivable to save valuable time and resources by automatically applying incoming payments to open receivables during daily batch processing. You can easily and efficiently resolve unapplied remittances online.

Advanced Remittance Processing (ARP) is an automatic cash application process that allows you to perform the following functions:

12345679Last

Theme picker

Tips: LN | Baan

A cash flow statement provides a historical view of the movement of cash within a company. This statement offers an overview of both the origins and destinations of cash, aiding management in evaluating the company's ability to fulfill short-term financial obligations. To differentiate between various sources and uses of cash, reason codes can be utilized. When interacting with cash transactions in relevant sessions, users have the option to input or review the corresponding cash flow reason. The cash flow statement organizes cash transactions based on these reasons. LN software system maintains year-specific opening balances for cash flow transactions. Should the need arise, users can manually input opening balances in the Opening Balance Cash Flow (tfgld2118m000) session.

To set up the cash flow statement, use the following sequence of sessions:...

When there are two Cost Items, one with Release to Warehousing applied and the other with Release to Warehousing not applied, upon approval of the Sales Order, the Cost Item that is released to Warehousing will go straight to Staged status, pending Shipment confirmation, while the Cost Item that is not released to Warehousing will be up for Sales Deliveries.

Apart from this main difference in functionality between having and not having this option to release to Warehousing checked, there are other impacts to consider...