BPCS/LX Tip of the Week: Changing the Master Schedule

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Previous Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Next Article PDIC selects NextTrack Dashboard for Costa Rica Wire Plant
Print
48741 Rate this article:
4.5
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

Advanced Remittance Processing, ARP, provides an automated approach to your cash application process. ARP works together with Accounts Receivable to save valuable time and resources by automatically applying incoming payments to open receivables during daily batch processing. You can easily and efficiently resolve unapplied remittances online.

Advanced Remittance Processing (ARP) is an automatic cash application process that allows you to perform the following functions:

12345679Last

Theme picker

Tips: LN | Baan

A cash flow statement provides a historical view of the movement of cash within a company. This statement offers an overview of both the origins and destinations of cash, aiding management in evaluating the company's ability to fulfill short-term financial obligations. To differentiate between various sources and uses of cash, reason codes can be utilized. When interacting with cash transactions in relevant sessions, users have the option to input or review the corresponding cash flow reason. The cash flow statement organizes cash transactions based on these reasons. LN software system maintains year-specific opening balances for cash flow transactions. Should the need arise, users can manually input opening balances in the Opening Balance Cash Flow (tfgld2118m000) session.

To set up the cash flow statement, use the following sequence of sessions:...

When there are two Cost Items, one with Release to Warehousing applied and the other with Release to Warehousing not applied, upon approval of the Sales Order, the Cost Item that is released to Warehousing will go straight to Staged status, pending Shipment confirmation, while the Cost Item that is not released to Warehousing will be up for Sales Deliveries.

Apart from this main difference in functionality between having and not having this option to release to Warehousing checked, there are other impacts to consider...

First45679111213Last

Theme picker

Categories