Infor LX & BPCS Tip: How to handle “ZERO COST” items

When I try to enter a 3-way match invoice with zero cost items, I get an error 'Must have value/cost entry.

Resolution
ACP500 requires a positive value to create a 'C' transaction when entering a 3-way match invoice. If you are receiving inventory items for free (no charge) and have a purchase order for it and need to include the quantity in inventory, you should first receive your items through PUR550 using something like a 'U' transaction. Then, you would enter a 'C' transaction with the quantity and zero cost through PUR550. This will change the status of the line in the HPO file to '3', fully received and costed. Once this is completed, you will be able to enter an invoice for your zero-cost item through ACP500 without getting the error message 'Must have value/cost entry.

Previous Article Infor LN & Baan Tip: MPS Planned vs. MRP Planned
Next Article Infor LN & Baan Tip: Why was the session "General Ledger Diagnostics Workbench" built?
Print
6355 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan/LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error. It is recommended that the Integrations Setup tables be audited either through Baan or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

In LN, you can differentiate between items at various suppliers:

  • Locations (warehouses),
  • Purpose (planning, purchase)
  • Origin (supplier, warehouse)

Example

An item is supplied by two different suppliers. Supplier A ships in lots of 100 pieces due to how the item is packed. Supplier B ships the goods in units of 60 pieces.

You can define specific parameters for each supplier. The following sessions can be used to define these characteristics:
 
  • Items - Planning (cprpd1100m000)
  • Check Item Data by Warehouse (whwmd2210m000)
  • Item Supplier Plan (cpvmi0530m000)
These sessions define entities that have an n-to-1 relationship with the general item data.

 