Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan/LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error. It is recommended that the Integrations Setup tables be audited either through Baan or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

In LN, you can differentiate between items at various suppliers:

  • Locations (warehouses),
  • Purpose (planning, purchase)
  • Origin (supplier, warehouse)

Example

An item is supplied by two different suppliers. Supplier A ships in lots of 100 pieces due to how the item is packed. Supplier B ships the goods in units of 60 pieces.

You can define specific parameters for each supplier. The following sessions can be used to define these characteristics:
 
  • Items - Planning (cprpd1100m000)
  • Check Item Data by Warehouse (whwmd2210m000)
  • Item Supplier Plan (cpvmi0530m000)
These sessions define entities that have an n-to-1 relationship with the general item data.

 

First144145146147149151152153Last

Theme picker

Categories