Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

Advanced Remittance Processing, ARP, provides an automated approach to your cash application process. ARP works together with Accounts Receivable to save valuable time and resources by automatically applying incoming payments to open receivables during daily batch processing. You can easily and efficiently resolve unapplied remittances online.

Advanced Remittance Processing (ARP) is an automatic cash application process that allows you to perform the following functions:

12345678910Last

Theme picker

Tips: LN | Baan

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

In Baan IV, a distinction is made between the actual ERP system and a separate planning tool which contains the Constraint Planning package. This tool was intended to work with any ERP system, not just with Baan IV. The Enterprise Planning package is now considered to be a package like any other package in Infor LN.

Users of Baan IV could choose whether they wanted to plan their supply in one of the following ways:

  • By using the MPS and MRP modules in the Manufacturing package.
  • By using the RPD and RMP modules in the Constraint Planning package.

Users of Infor LN can only use the Enterprise Planning package. The distinction between the MPS items and MRP items has been abandoned. In Infor LN, all items can be planned by using a combination of master-based planning methods and order-based planning methods.