Baan/LN Tip of the Week: The Product Configurator

Kathy Barthelt 0 45398 Article rating: No rating

What is it?
The configurator consists of a set of features (questions). The options (answers) to these questions are used to generate the custom bill of material and routing. These questions may be answered at the time of order entry, prior to order entry (in a project or quote) or after order entry (in the project). The order of the questions do not need to have any relationship to the bill of materials. The configurator may also calculate the selling price, create a unique “smart” item number, custom description and text. Simple rules are used to interpret the answers.

Who uses the configurator?
Companies whose products have options. The configurator eliminates the need for part numbers for all combinations of options. The configurator ensures that the pricing and bills are correct. The configurator also keeps statistics on the frequency the options are selected.

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Anthony Etzel 0 17146 Article rating: No rating

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have set up your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished, and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are set up and what transactions along with their frequency are captured.

PDIC selects NextTrack Dashboard for Costa Rica Wire Plant

Anthony Etzel 0 41724 Article rating: No rating

The Analytics Dashboard will be used in combination with the existing Crossroads MES system to provide real time machine status across the plant. In addition, KPI’s like OEE and Downtime % will be monitored and displayed at the wire machines and to the production management.

BPCS/LX Tip of the Week: Changing the Master Schedule

Anthony Etzel 0 50065 Article rating: 4.5

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 56440 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 61687 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 45904 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 38237 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

RSS
First159160161162163164165167

Theme picker

Tips:  LX | BPCS | M3

Finance: Cost Rollup by Effective Date
Allow the load standard cost from routing and cost rollup programs to process as of a specified effective date.  With the addition of an optional effective date parameter to prompt screens for cost rollup CST500 and load standards from routing CST600. If entered, only consider bill of material components and routing operations with effective and discontinue dates that make them effective as of the entered parameter effective date.


Operations: Outside Operation Purchase Order Include Vendor Item Number
Copy the vendor item number from the vendor quote to purchase orders created automatically from outside operations of shop orders. During the process of automatically creating purchase orders from outside operations of shop orders, copy the vendor item number from the vendor quote to the purchase order line. With this change, looking at a purchase order that was created automatically for an outside operation of a shop order, the vendor item number from the vendor quote will be visible on the purchase order line.


Technology: Group Security for ILM501 Inbound Delivery Maintenance
Add function key / action code security to control who is authorized to create/revise/delete functions in ILM501 Inbound Delivery Maintenance.  With added Group Security, managers can control which users are authorized to create, change and delete deliveries in ILM501 Inbound Delivery Maintenance.

12345678910Last

Theme picker

Tips: LN | Baan

Infor LX & BPCS Tip: Vendor Terms Maintenance, ACP160D1

This program allows maintenance of vendor terms, which you individually assign to each vendor. Vendor terms designate the due date and the discount date as a number of days after the invoice date. You establish the discount percentage here. Vendor terms are stored in the AVT file. Rather than use the method specified above, you can override due dates and discount dates so those calendar days are used to age invoices.

Access: Menu ACP02