Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 60208 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 44865 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 37289 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 69598 Article rating: 5.0

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 55669 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 56273 Article rating: No rating

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Crossroads MES Version 11 Released

Anthony Etzel 0 38733 Article rating: No rating

Crossroads MES Version 11 was rolled out in March, 2014. Some of the new features include a new GUI interface, improved End of Shift review functions, pre-formatted production label printing, and an electronic shop packet on the factory worker Job In screen.

Crossroads MES Released for Tablet

Anthony Etzel 0 35048 Article rating: 3.7

Crossroads RMC announces that the Crossroads MES solution is now compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

RSS
First157158159160161162163164166

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

Avoid Being a Quitter: How Crossroads RMC Can Help You Achieve Your Goals

Unlocking Success Infor LX/BPCS & Infor LN and Baan

Avoid Being a Quitter

As the calendar flips to January 1st, it marks the beginning of a new year filled with fresh opportunities and resolutions. It's that time when many of us set ambitious goals for ourselves, both personally and professionally. But, how often do these aspirations fizzle out before we even hit the second Friday of the year? It's so common that they even call it "Quitter's Day." However, it's not too late to stay on track and realize your ambitions. In this article, we'll focus on the professional side of goal-setting and how Crossroads RMC can be your ally in achieving manufacturing excellence.

Step 1: Make Your Goals Bite-Sized

While you might have grand ambitions, like upgrading your ERP system, increasing customer satisfaction, or optimizing your supply chain, achieving these goals often involves breaking them down into smaller, manageable projects. Here's how you can start:

  • Why: Understand why you want to make these changes. Is it to retain your top customers, leverage new ERP features, or streamline your supply chain?
  • What: Clearly define the desired outcomes – be it increased sales, enhanced efficiency, or cost reduction.
  • Who: Identify the key players who can help you achieve these goals. Do you have the necessary resources in-house, or should you consider external expertise?
  • When: Establish a timeline, considering your overall company initiatives, project priorities, and deadlines. Make your goals specific, measurable, attainable, and time-based (SMART).

For example:

  • Increase customer satisfaction for our top 5 customers by 10% in the next 6 months.
  • Reduce production mistakes in our welding department by 50% within a year.


Step 2: Identify Roadblocks

What's preventing you from reaching your goals? Is it a lack of resources, support, or the right tools? Consider these factors:

  • Lack of bandwidth: Assess your team's capacity. Can you involve colleagues from other departments or partners?
  • Support: Get buy-in from business leaders by demonstrating the ROI and benefits of your project. Educate your coworkers on its importance.
  • Tools: Explore features in your ERP system that you might not be utilizing fully. Is an upgrade or additional software add-ons needed?

 
Step 3: Take Action and Persist

Creating a plan is vital, but remember, the path to success isn't always smooth. Prepare for challenges and adapt as needed:

  • Develop a comprehensive plan to execute your goals.
  • Communication is key. Keep your team informed about progress and challenges.
  • Adjust your plan when necessary. Mistakes are part of the journey and can lead to future success.


How Crossroads RMC Can Help You in 2024

At Crossroads RMC, we understand the challenges manufacturers face, and we're here to support your journey to success. Here's how we can assist:

  • Implement new functionality in your existing ERP system.
  • Lead the way in upgrading your ERP to the latest version.
  • Provide training based on best practices for your employees.
  • Automate time-consuming, manual processes.
  • Integrate your systems, creating a seamless, cohesive environment.
  • Deliver ERP add-on solutions that save you time and money.

We offer a comprehensive range of consulting services and software designed to optimize manufacturing by reducing costs, improving quality, and enhancing efficiency.

Learn More:

Infor LX & BPCS Services> Infor LX & BPCS Software>

Infor LN & Baan Services> Infor LN & Baan Software>
 

It's Time for Action!

Contact us today at solutions@crossroadsrmc.com or call us at 800.762.2077 to discuss your ERP goals. Let Crossroads RMC be your partner in making 2024 a resounding success for your manufacturing business!

Print
4556 Rate this article:
.2
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

x

Categories