Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 60027 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 44717 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 37146 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 69452 Article rating: 5.0

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 55514 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 56090 Article rating: No rating

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Crossroads MES Version 11 Released

Anthony Etzel 0 38577 Article rating: No rating

Crossroads MES Version 11 was rolled out in March, 2014. Some of the new features include a new GUI interface, improved End of Shift review functions, pre-formatted production label printing, and an electronic shop packet on the factory worker Job In screen.

Crossroads MES Released for Tablet

Anthony Etzel 0 34898 Article rating: 3.7

Crossroads RMC announces that the Crossroads MES solution is now compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

RSS
First157158159160161162163164166

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Year-End Processing Checklist for Period and Fiscal Year Closure

The conclusion of the fiscal year is inevitably a hectic period, making it crucial not to overlook essential tasks within your ERP system to ensure a seamless year-end close and set the stage for a successful start to the upcoming year. Below are critical items to include in your comprehensive checklist:

Year-End Close Process:

  1. Remove discontinued items.
  2. Eliminate sold purchase receipts.
  3. Clear lot attributes for sold lots.
  4. Update standard cost based on the current cost field (for environments without Manufacturing only).

Prepare for Year-End Close:

  1. Conduct a comprehensive physical inventory and update quantities before the actual year-end or establish a robust cycle-counting program.
  2. Review and post any applicable sales and purchase invoices/returns.
  3. Prepare users for a year-end push to complete all year-to-date inventory adjustments, receipts, and invoicing.
  4. Determine procedures for handling new year transactions without immediate posting.
  5. Establish new standard costs for the upcoming year (Manufacturing).
  6. Discuss cutoff dates for removing Archived BOMs and Closed/Canceled Mfg Orders (Manufacturing).

Finance Specific Items:

  1. Set up financial periods for 2024 (fiscal, reporting, and tax, as applicable).
  2. Open January period in 2024.
  3. Finalize any outstanding transactions from the current year (2023).
  4. Perform a soft-close for any open periods in 2023.

General Baan/LN Tips:

  1. Issue any pending old sales invoices.
  2. Resolve outstanding financial integration errors.
  3. Establish new integration mapping for 2024 as needed.
  4. Test the mapping in a controlled environment before the new year.
  5. Review and update jobs to ensure they will process in 2024.
  6. Determine, for cash-flow purposes, which purchase invoices won’t be paid until 2024.
  7. Verify that calendars are set up for the new year with holidays correctly indicated.
  8. Check jobs to ensure that any with hard-coded dates will point at the new year.

For additional insights and tips on year-end processing, refer to the relevant documents in the Infor Knowledge Base.

 KB 

 Content 

 1879191  

 Document including step by step procedure, possible error/warning messages, and more (Infor LN) 

 1147023 

 Step by step procedure description (Infor LN)

 1116239 

 Step by step procedure description (Infor LN)

 1117334

 Step by step procedure description (Infor LN; Portuguese)

 1171300 

 Step by step procedure description (Baan IV) 

If you require assistance or have any questions, feel free to reach out to us, and we'll gladly guide you through the necessary steps to ensure a thorough and accurate completion of your year-end processes. Contact us at 1.800.762.2077 or via email at solutions@crossroadsrmc.com. Your success is our priority, and we're here to help.

Previous Article Infor LN & Baan Tip: When is backflushing disabled in LN?
Next Article Infor LX / BPCS & Infor LN / Baan Tip: Time for the Notorious TRIO: Manual -  Physical -  Inventory
Print
6176 Rate this article:
2.5
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories