Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

BPCS/LX Tip of the Week: How To Capture Re-Work Time (Part 1)

Anthony Etzel 0 43180 Article rating: No rating
In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.

BPCS/LX Tip of the Week: Configuration Management

Anthony Etzel 0 44136 Article rating: No rating

Make to Order? No problem if you use the Configuration Management System. This LX product allows you to define and configure a make to order product during Customer Order Entry. Basically, you have the option to create different products under the same common product item. You will get two completely different common end items that are configured from the same common parent.

The customer orders are planned and turned into shop orders for each end item with all the associated components. With an MES solution in place, the shop order side is easy to schedule and allows you to manage the shop floor.

Baan/LN Tip of the Week: Product Configurator - Part 1

Kathy Barthelt 0 54832 Article rating: No rating
What is it?
The configurator consists of a set of features (questions). The options (answers) to these questions then are used to generate the custom bill of material and routing. These questions may be answered at the time of order entry, prior to order entry (in a project or quote) or after order entry (in the project). The order of the questions need not have any relationship to the bill of materials. The configurator may also calculate the selling price, create a unique “smart” item number, custom description and text. Simple rules are used to interpret the answers.

Who uses the configurator?
Companies whose products have options. The configurator eliminates the need for part numbers for all combinations of options. The configurator ensures that the pricing and bills are correct. The configurator also keeps statistics on the frequency the options are selected.
RSS
First154155156157159161162163Last

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Project Status Options

Ever wonder what the implications are of choosing one project status versus another?

Here is the explanation of project status possible values:

Free
You can carry out project engineering. This means that you can:

  • Define the project master schedule (PMS) by using the Project Control module.
  • Maintain the project structure.
  • Maintain the customized product structure by using customized bills of material and routing sheets.
  • Carry out project estimating.

Simulated
You simulate the rough capacity requirements planning and the detailed material and resource requirements planning (RRP) based on the network planning. The capacity requirements for a simulated project are visualized separately. Infor LN (ERP LN) generates planned RRP purchase orders, planned production orders, and PRP warehouse orders for customized items. However, those orders cannot be released. Moreover, the RRP does not allocate standard items to the project.

Active
This status indicates the project's execution stage. You can release planned orders so that the required purchase and production activities can be actually started and completed.

Canceled
The project has been canceled. You cannot release new orders for the project, but you can, however, finish pending logistical activities. You can close a canceled project, but a project can also remain canceled. If the project remains canceled, be aware that the final costs are not posted to Financials, and that WIP can still exist for completed orders. Costs are only posted if you close the project.

Finished
As far as manufacturing is concerned, the project is finished. Also, all purchase and production activities have been completed or closed, and all sales orders have been delivered for the project.

Closed
Financially, the project has been closed. This means that the financial project results have been computed. Financial project transactions can no longer be posted to the project.

To be Closed
If you select the COGS and Revenues restricted to Financial Company of PCS Project check box in the Project Control Parameters (tipcs0100m000) session, financial transactions are posted on the financial companies of the sales office, service department, and/or warehouse instead of on the financial company of the PCS project. If internal invoices are sent from the PCS project to those departments, and the internal invoices are not completed yet, the Close Project (tipcs2250m000) session sets the project status to To be Closed instead of to Closed. You must first complete the internal invoices, and then run the Close Project (tipcs2250m000) session again to set the project status to Closed.

Archived
The project has been archived. This means that all project data has been stored in archive files and is removed from the original files.

Previous Article Infor LN & Baan Tip: LN Order Management - Generating Purchase Receipts
Next Article Infor LN & Baan Tip: Cost Component Setup
Print
13200 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories