Anthony Etzel 0 43188 Article rating: No rating
In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.

BPCS/LX Tip of the Week: Configuration Management

Anthony Etzel 0 44145 Article rating: No rating

Make to Order? No problem if you use the Configuration Management System. This LX product allows you to define and configure a make to order product during Customer Order Entry. Basically, you have the option to create different products under the same common product item. You will get two completely different common end items that are configured from the same common parent.

The customer orders are planned and turned into shop orders for each end item with all the associated components. With an MES solution in place, the shop order side is easy to schedule and allows you to manage the shop floor.

Baan/LN Tip of the Week: Product Configurator - Part 1

Kathy Barthelt 0 54840 Article rating: No rating
What is it?
The configurator consists of a set of features (questions). The options (answers) to these questions then are used to generate the custom bill of material and routing. These questions may be answered at the time of order entry, prior to order entry (in a project or quote) or after order entry (in the project). The order of the questions need not have any relationship to the bill of materials. The configurator may also calculate the selling price, create a unique “smart” item number, custom description and text. Simple rules are used to interpret the answers.

Who uses the configurator?
Companies whose products have options. The configurator eliminates the need for part numbers for all combinations of options. The configurator ensures that the pricing and bills are correct. The configurator also keeps statistics on the frequency the options are selected.
RSS
First154155156157159161162163Last

Theme picker

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: MPS planned vs. MRP planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate cumulative lead time (also called “the Critical Path”) for you.

Infor LN does not differentiate between the two. Here, it is simply an enterprise planning EP with one set of planned orders. It is possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists both in purchase and manufactured planned items. It has both non-critical and critical lead times based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V
Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN
Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Previous Article Infor ERP Tip: Is your Infor ERP system up to date with all of the sales tax changes for 2021?
Next Article Infor LN & Baan Tip: Remove Posted Payment/Direct Debit Batches
Print
23373 Rate this article:
4.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories