BPCS/LX Tip of the Week: Shop Order Release Date

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Previous Article Infor Next Houston – Ming.le Update 11.0.1
Next Article Infor Next Houston – Industrial Manufacturing Solutions for Increased Complexity
Print
31877 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

1234567810Last

Theme picker

Tips: LN | Baan

When there are two Cost Items, one with Release to Warehousing applied and the other with Release to Warehousing not applied, upon approval of the Sales Order, the Cost Item that is released to Warehousing will go straight to Staged status, pending Shipment confirmation, while the Cost Item that is not released to Warehousing will be up for Sales Deliveries.

Apart from this main difference in functionality between having and not having this option to release to Warehousing checked, there are other impacts to consider...

First567810121314Last

Theme picker

Categories