Baan/LN Tip of the Week: Company Calendar

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

Previous Article BPCS/LX Tip of the Week: SFC600 & SFC650
Next Article Infor and Crossroads RMC are proud to offer a joint webinar on Taking Your Shop Floor Paperless - August 28th, 2014.
Print
55729 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Did you know that you can set up one-time vendors in LX? One Time Vendor (1,A): Specify Y to indicate that this vendor is a one-time vendor. Otherwise, could you specify N. The system removes a one-time vendor's information from the Vendor Master file after all transactions are reconciled. If this vendor already exists as a one-time vendor, you can specify N to change the vendor to a regular vendor.

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

1234567810Last

Theme picker

Tips: LN | Baan

When there are two Cost Items, one with Release to Warehousing applied and the other with Release to Warehousing not applied, upon approval of the Sales Order, the Cost Item that is released to Warehousing will go straight to Staged status, pending Shipment confirmation, while the Cost Item that is not released to Warehousing will be up for Sales Deliveries.

Apart from this main difference in functionality between having and not having this option to release to Warehousing checked, there are other impacts to consider...

First567810121314Last

Theme picker

Categories