Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 104216 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 82358 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 110246 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 81714 Article rating: No rating
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

BPCS/LX Tip of the Week: The Item Master Requirements Code

Anthony Etzel 0 76644 Article rating: No rating

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

Grindmaster Cecilware Selects Crossroads RMC For Baan IV / Davisware Integration

Crossroads RMC 0 41041 Article rating: No rating

Grindmaster Cecilware, a leader in the development of products for the food and beverage industry, has selected Crossroads RMC to integrate their Baan IV system to Davisware Global Warranty. Davisware is an electronic customizable online solution that fits almost any warranty process. Grindmaster’s customers will be able to access the Davisware software online and process warranty claims which will then automatically feed back into the Baan IV system for further review and processing. The integration is expected to go live in Q1 of 2015.

First119120121122124126127128Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Don't laugh - the average lifespan of an ERP system is 7-10 years

Don't laugh - the average lifespan of an ERP system is 7-10 years

Don’t laugh! I know, I know…many of our customers say that after 7-10 years they are finally settling in after the implementation! We have seen many a customer stretch out the lifespan of their ERP system to 20+ years. That sounds great for the company’s bank account, but is it good for the business?

An outdated ERP system hurts your business in many ways, not just with slow performance. The best-of-breed functionality is now 2 decades old, and obsolete technology can't leverage newer technology. Lack of integration leads to siloed data that hurts communication and your internal teams feel the pain, and your customers are noticing. Poor visibility into your operations makes it nearly impossible to achieve industry-based regulatory compliance and meet financial auditing requirements. Not to mention the sheer size of Big Data that is being collected today vs. 2 decades ago or the fact that your vendor is no longer supporting your ERP version.

Let’s scrap it all and start over!

Is it that black and white though? There is an ocean between “do nothing” and “replace everything”. Taking incremental steps can give your organization a tremendous amount of benefit without the tremendous price tag that often goes with ERP replacement, but you need to be willing to take the first step. Maybe there is a manufacturing ERP add-on that you know would provide tremendous benefit and improve overall efficiency, or a web portal that you log in to that allows you to communicate with your suppliers, but it has no tie to your purchase orders, or maybe your team would benefit from a review of industry best practices and how that compares to how your ERP system is currently being used. Or at the very least you need to know if your ERP system is still meeting the organization’s needs.

Success will never be a big step in the future. Success is a small step taken just now.” – Jonatan Martensson

Crossroads RMC specializes in helping manufacturers maximize the benefit of “the small step”.  Not sure how Crossroads RMC can optimize your business?

Our Infor ERP Services can optimize your business with the following initiatives and many more:

Infor LX (ERP LX) Services>
Infor LN (ERP LN) Services>
BPCS Services>
Baan Services>

It's time to take the first step today!
800-762-2077  |  solutions@crossroadsrmc.com

Previous Article Infor LN & Baan Tip: Purchase Order Text
Next Article Infor LN & Baan Tip: Important Porting Set Announcement (all versions of LN & Baan)
Print
33796 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories