Baan/LN Tip of the Week: Sales Order Acknowledgements

Kathy Barthelt 0 3109 Article rating: No rating

Sales Order Acknowledgements in Baan IV:
After a sales order is entered in Baan IV, users can print an order acknowledgement in Print Sales Order Acknowledgements/RMAs (tdsls4401m000), after which it can be sent to the customer.

Sales order acknowledgements in ERP LN:
In Infor LN, users can still use the Print Sales Order Acknowledgements/RMAs (tdsls4401m000) session to print order acknowledgements, however, the following functionality is added to this session:

  • In the Documents to Print field users can select whether to print order acknowledgments and/or return material authorizations.
  • With the Promotions check box users can indicate whether to print promotions on the order acknowledgement, if promotions apply to the order.
  • Users can control the printing of order acknowledgements based on the order amount and/or the delivery date.

These conditions only apply for order types that do not have the Print Sales Order Acknowledgements/RMAs (tdsls4401m000) linked as a mandatory activity to the order type in the Sales Order Type - Activities (tdsls0560m000) session.

BPCS/LX Tip of the Week: Operational Inefficiencies

Anthony Etzel 0 393 Article rating: No rating

Two big sources of inefficiencies in manufacturing are paper and spreadsheets. I know that you love ‘em, but they are the cause of more problems than you probably realize. Think of how long it takes you to get paper based data into the hands of those who can do something valuable with the data. Are you capturing all of the information correctly? Timely? What about those spreadsheets? Can everyone access that information across your organization? Is that data married with all of the related data regarding your operations to give your executive and middle management the information they need when they need it?

Make your shop floor paperless and put in place systems that talk to one another and automatically pull and push data to and from your ERP so that you can look in one place for all the information you need to run your business effectively.

If you’re not doing this today, you might as well be burning money.

Baan/LN Tip of the Week: Use of Correction Period

Kathy Barthelt 0 173 Article rating: No rating

There can only be one correction period, and it must be the last period in the period table.

There can only be a correction period for Fiscal periods and not for Reporting or Tax. This period is used for the posting of the Automatic Balancing of Profit and Loss entries as well as any auditor adjusting entries that may be made outside the normal year. This allows you to print a trial balance and financial statements of period 1-12, for example, eliminating any of those adjusting entries.

If you have the Company Parameter (Balancing of Profit & Loss) set to Individual Accounts, then it is critical to have a 13th period to post those entries to. With this setting, the Automatic Balancing will zero out each individual P&L account in the last period. You want this to be period 13 and not period 12.

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Anthony Etzel 0 346 Article rating: No rating

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 178 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: Indirect Time

Anthony Etzel 0 1002 Article rating: No rating

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.
 

  1. If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  2. If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

 

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

 

10 Ways to Not Screw Up the OEE Project – It is More Important than You Think

Rich Grilli 0 37681 Article rating: 5.0


Is there a mandate in your company to increase OEE and it has landed on your plate? Ah yes, the OEE approach. You remember what that is right? The Overall Equipment Effectiveness  metric as developed in Japan during restoration made famous in crafting some serious efficiency. Well, someone in management has decided that this is the way to make his world better and now it’s up to you to make it happen.

But there are pitfalls along the way:

First116117118119121123124125Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Don't laugh - the average lifespan of an ERP system is 7-10 years

Don't laugh - the average lifespan of an ERP system is 7-10 years

Don’t laugh! I know, I know…many of our customers say that after 7-10 years they are finally settling in after the implementation! We have seen many a customer stretch out the lifespan of their ERP system to 20+ years. That sounds great for the company’s bank account, but is it good for the business?

An outdated ERP system hurts your business in many ways, not just with slow performance. The best-of-breed functionality is now 2 decades old, and obsolete technology can't leverage newer technology. Lack of integration leads to siloed data that hurts communication and your internal teams feel the pain, and your customers are noticing. Poor visibility into your operations makes it nearly impossible to achieve industry-based regulatory compliance and meet financial auditing requirements. Not to mention the sheer size of Big Data that is being collected today vs. 2 decades ago or the fact that your vendor is no longer supporting your ERP version.

Let’s scrap it all and start over!

Is it that black and white though? There is an ocean between “do nothing” and “replace everything”. Taking incremental steps can give your organization a tremendous amount of benefit without the tremendous price tag that often goes with ERP replacement, but you need to be willing to take the first step. Maybe there is a manufacturing ERP add-on that you know would provide tremendous benefit and improve overall efficiency, or a web portal that you log in to that allows you to communicate with your suppliers, but it has no tie to your purchase orders, or maybe your team would benefit from a review of industry best practices and how that compares to how your ERP system is currently being used. Or at the very least you need to know if your ERP system is still meeting the organization’s needs.

Success will never be a big step in the future. Success is a small step taken just now.” – Jonatan Martensson

Crossroads RMC specializes in helping manufacturers maximize the benefit of “the small step”.  Not sure how Crossroads RMC can optimize your business?

Our Infor ERP Services can optimize your business with the following initiatives and many more:

Infor LX (ERP LX) Services>
Infor LN (ERP LN) Services>
BPCS Services>
Baan Services>

It's time to take the first step today!
800-762-2077  |  solutions@crossroadsrmc.com

Previous Article Infor LN & Baan Tip: Purchase Order Text
Next Article Infor LN & Baan Tip: Important Porting Set Announcement (all versions of LN & Baan)