Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?

Kathy Barthelt 0 49779 Article rating: 5.0

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Infor LX / BPCS Tips & Tricks for Finance: Inventory Period Balance Freeze

George Moroses 0 17953 Article rating: 5.0

Users can now freeze period-end balances at the end of a fiscal period. You can now store the opening/ending on hand balance for each Inventory period at the Item (IIM), Warehouse/Item (IWI) and Lot/Location (ILI) levels. This information can then be used for inventory tracking and valuation purposes, as well as other ad hoc financial and audit reporting requirements. Infor LX clients can backdate inventory transactions into the immediate previously closed period, and thus update what was saved as the opening/ending balance throughout the current open period.

Infor LX / BPCS Tips & Tricks for Operations: Retain Lot Status on Shipped Resupply Orders

George Moroses 0 12970 Article rating: 5.0

When a lot is completely shipped on a customer order, the Lot Status is changed to Z. Since a resupply order must still be received in the To Warehouse to complete the transaction, do not update the lot status when the resupply order is shipped. If a lot is completely shipped on a resupply order, LX no longer updates the lot status to Z, because the shipped lot retains its current lot status, the additional steps, no additional steps are required to receive it in the To Warehouse.

Infor LX / BPCS Tips & Tricks for Technology: Reset Purchase Order In Use

George Moroses 0 13920 Article rating: 5.0

This feature resolves or resets a purchase order or requisition that is no longer being processed, but the system still indicates it is 'in use'. The user selects Purchase Order/Requisition in Use Maintenance, PUR940D, from the Purchasing Management Menu, PUR, located in the Special Processing sub-menu. The user then enters an order or requisition to remove the 'In Use' status.

End of Year E R P Checklist: Streamline Your Transition to the New Year

Crossroads RMC 0 6958 Article rating: 5.0

The end of the year is a busy time for everyone, but a little preparation can make the start of the next year smoother and more productive. Here's a checklist broken out by the department to help optimize your ERP system as you wrap up this year.

  1. All Departments Checklist
  2. Technology Checklist
  3. Operations Checklist
  4. Finance Checklist
First34568101112Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Infor LN & Baan: BIG DATA - Keeping Track of Key Metrics

In order to communicate effectively as a team, everyone needs to speak the same language and operate off the same playbook. If decisions are made based on the data or the view of data that individuals are maintaining through their own spreadsheets or other data silos, then communication is negatively impacted.

Manufacturers need to review large amounts of data every day, making it difficult to keep track of key metrics within your department.

That’s where Crossroads RMC’s Analytics Dashboard solution comes in. Our Analytics Dashboard was developed to make tasks easier by putting all of the key information in one convenient location so you can view all of your crucial data in real-time.
 

With powerful dashboards, you can:

  • Create pie charts, graphs, interactive maps, and more with just a few clicks.
  • Build a dashboard once and make it instantly available on any device.
  • Tell a story with your data with your own custom layouts, colors, and commentary—all with no coding.
  • Confidently provide reports with real-time data updates.
  • Access your dashboards from anywhere–computer, tablet, or phone.

Check out the sample of our dashboards by department below. Then, to get started, request a demo for a complete walkthrough of our Analytics Dashboard.
 

Manufacturing

OEE, time usage, downtime, quantities, cycle times, and more...

Enlarge Production Summary Dashboard Enlarge Work Center Job Step Status
Production Summary Dashboard Machine / Labor Performance Dashboard Work Center Job Step Status Dashboard



Finance

Revenue, income, working capital, assets, and more...

Enlarge Accounts Receivable Dashboard
Accounts Receivable
Summary Dashboard
Accounts Receivable
Dashboard
Enterprise Accounting
Dashboard


Materials

Planning, sourcing, procuring, transporting, storing, controlling materials, and more...

Enlarge Inventory Dashboard Enlarge Sales History Dashboard
Inventory Dashboard Purchasing Dashboard Sales History Dashboard

Learn more>
 

Contact us or Request a demo to Get Started.

Previous Article Infor LN & Baan Tip: How to deal with data growth of your ERP system…
Next Article Infor LN & Baan Tip: Backflushing of Materials & Hours
Print
59728 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories