Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Industry News: Technology - The Secret Life of the American Factory

Crossroads RMC 0 46247 Article rating: No rating

New Data: New Fruit…that’s the promise of finding new data sitting right there under your nose on the factory floor.

Doug Woods, president of the Association for Manufacturing Technology and MTConnect champion says it this way:
"At the end of the day," he explains, "after you've invested in hardware and machines, at some point it all comes down to how do you wring the maximum amount of productivity out of them? How do you get the ultimate efficiency out of the facility?" The only way to be confident you're doing that, he says, is to really understand what is going on with all of the equipment in the factory all of the time. And that, he says, comes down to having "really good data." 

Read Full Article>

Discover How Crossroads RMC can meet this need with Analytics Dashboard.

Baan/LN Tip of the Week: Project Templates

Kathy Barthelt 0 88871 Article rating: No rating

Project templates are useful because you can specify all of the information that you would normally want to include when creating a new project such as project structure, budget, and so on.

In Baan IV/V, project templates do not exist, but you can set up a project template by creating a regular project, and setting the status to simulated or free. This is done so that the project does not create plans. Under this scenario, you can easily copy one project to another.

In LN, when you create a new project, a template can be used as the starting point. This is similar to copying a normal project, but unlike normal projects, no costs or revenues can be posted on a template.

BPCS/LX Tip of the Week: Work Center - Cells

Anthony Etzel 0 90147 Article rating: No rating
The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

BPCS/LX Tip of the Week: The Machine Master Part 2

Anthony Etzel 0 86846 Article rating: No rating
Understanding:

The Machine Master File

Do your machines have a fixed asset tag? The machine master file has a field called Fixed Asset.

BPCS does not use this field, so you can use this field for anything. You can record your fixed asset tag in this field and use the effective date. You can create a custom fixed asset list by using a DFU or Query program.

Baan/LN Tip of the Week: Business Partner Structures

Kathy Barthelt 0 95240 Article rating: No rating

In ERP LN, users can define a distributed business partner organization by defining parent business partners to link the business partners with different roles.

In Baan IV, users can define a distributed business partner organization in the Maintain Concern Structure of Trade Relations (tccom3101m000) session.

Harsco Rail Goes Live With the RMC3 Data Collection Solution

Crossroads RMC 0 38822 Article rating: No rating

Harsco Rail, an industry leader in the railway track maintenance, has completed the first phase of their implementation of the Crossroads RMC Data Collection Solution for Baan V. The initial implementation included receiving and putaway. Harsco’s data collection project manager reports, “When I ask them (the users) how it’s going, they smile. I have had nothing but very positive feedback. It’s been very uplifting for me to work on this project and have it so well received.” The next phase of the implementation will include Report Operations Complete, Inventory Transfers, and Stock Inquiry.

Baan/LN Tip of the Week: Tax Exemption Certificates

Kathy Barthelt 0 87357 Article rating: No rating

In Baan IV, tax exemption processing is supported only on sales orders for non-tax provider users.

In Infor LN, tax exemption certificate processing is also performed for purchase orders, and for sales orders if users use a tax provider.

Users can define tax-exemption certificates in the following sessions:

  • Tax Exemptions for Sales (tcmcs1142m000)
  • Tax Exemptions for Purchasing (tcmcs1560m000)
  • Register Warehouse for Tax Exemptions (tcmcs1561m000)

 

BPCS/LX Tip of the Week: The Machine Master Part 1

Anthony Etzel 0 84680 Article rating: No rating
Understanding:

The Machine Master File


Machines are associated with a work center. For example, in the work center you may have multiple machines and each machine can have a unique machine ID. If there are several machines that perform the same function, they may operate at different speeds and efficiencies. Setting up the machine master can be a benefit for planning capacity and shop order throughput.
First128129130131133135136137

Tips:  LX | BPCS | M3

Tips: LN | Baan

Infor LN / Baan Tips & Tricks for EXECUTIVES

Finance: Propagating Unused Sub-Accounts

You can use this procedure to find accounts that have a valid sub-accounts group but no corresponding general ledger chart account records. This action creates the general ledger chart account record for the account and sub-account combination. This action does not add the accounts to charts.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group and click the Sub Account tab.
  3. Select Actions > Propagate Unused Sub Accounts.
  4. Select the finance enterprise group and click OK.

Sub-accounts are added according to group if they have been defined on the accounts. The resulting account can be added to the charts.

Operations: Best Practices for Purchase Order Archiving / Deleting

Here are some best practices to follow if you are considering archiving or deleting purchase order data:

  • If Financials is implemented, we recommend that you do not delete order data in a fiscal year that has not yet been fully closed. This is because the GRINYA process uses information that would be deleted by this action. For best results, check whether the logistical balance for non-invoiced receipts matches the balance of the GRINYA accounts for the periods up to which you want to delete purchase order data.
  • When a purchase order is canceled, you can only delete the purchase order and the related tables. If only a purchase order line is canceled, the line can be deleted and archived.
  • Purchase contracts must be archived before purchase orders can be archived.

You cannot delete a purchase order (line) if:

  • The linked warehouse order is closed but cannot be removed.
  • The purchase order is linked to a PCS project that is not yet archived. When the PCS project is archived, the purchase data is also archived and you can delete the purchase order.
  • A consignment replenishment order is not yet consumed completely.
  • The invoice is yet to be completely matched and approved.
  • The invoice amount is not yet inserted as turnover history.
  • The sales order or service order that's linked to the purchase order line, and for which an internal invoice must be sent from the purchas office to the sales office or service office, is not yet invoiced. In this case, you cannot delete the purchase order line before the sales order or service order is invoiced.

Technology: Using Table Boosters to Speed Up Sessions & Processes

To increase the speed of sessions and processes slowed by large amounts of data, you can use table boosters. These speed up access to specific database tables by loading the table, or a specified part of it, into memory. Table boosters are defined in the Table Boosters (tcmcs0598m000) session.

Tables

Table boosters are implemented for tables. By default, table boosters are not active. When you access a table, LN builds a list of tables for which you can activate the boosters in the Table Boosters (tcmcs0598m000) session.

Note: You can only activate table boosters for tables that have been accessed at least once.

For more information, refer to the LN - Performance, Tracing, and Tuning Guide (U9357).

Previous Article Infor LN & Baan Tip & Tricks for OPERATIONS: Best Practices for Purchase Order Archiving / Deleting
Next Article Infor LN & Baan FINANCE Tip: Is it possible to upload accounts receivable invoices into LN using Excel?
Print
20565 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories