BPCS/LX Tip of the Day: Material Requirement Dates and Lead Time Offsets in MRP

Anthony Etzel 0 343 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Database Sizing – Moving to LN

Kathy Barthelt 0 219 Article rating: No rating
The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

How Do You Measure Success in Your Business?

Anthony Etzel 0 52950 Article rating: 5.0

Business owners may measure success in different ways – some tangible, some intangible.

In order to establish how you should measure success for your business, you need to first examine how you measure your personal success. If you are a business owner, or a part of the management team of the company you work for, ask yourself these questions to see how you measure up:

Assess personal success.

1.    Am I happy in my job?

2.    Do I have passion for what I’m doing?

3.    Do I get the desired results based on the effort I’m putting in?

4.    Am I putting forth my best effort?

5.    Am I patient and allow for sufficient time to see results?

6.    Do I get respect from my co-workers?

7.    Do I have the endurance to hang in there when things get a bit rough?


Reflect on successes and failures.

After answering these questions, do you need to make any changes? Do you still have the same ambition and drive to achieve the goal? Are you content with your work, or have you come to the conclusion that you have not done your best?

To be successful...

Baan/LN Tip of the Week: Switching to a Difference Series

Kathy Barthelt 0 204 Article rating: No rating

In general, you can enter a different series in the order field if you have an available series.

To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1). Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

BPCS/LX Tip of the Day: MRP/MPS Simulation

Anthony Etzel 0 786 Article rating: No rating
The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

BPCS/LX Tip of the Day: Inventory Stocking Levels – LX

Anthony Etzel 0 735 Article rating: No rating

The system supports four levels of inventory. You can view summaries of stock at each level through the Material Status Inquiry program or through reports.

 

Below are the four levels:

â–ª  Item

â–ª  Item + warehouse

â–ª  Item + warehouse + location

â–ª  Item + warehouse + location + lot

 

The lot number level and/or container of inventory can cross multiple warehouses and locations. For example, item + lot or item + lot + container. Locations exist within warehouses. There is no limit on the number of warehouses, locations, or lots that you can assign to an item.

Baan/LN Tip of the Day: Transfers - LN

Kathy Barthelt 0 2779 Article rating: No rating
A Transfer involves either one or two warehouses. If items are transferred between two different warehouses, all activities of the warehousing procedures must be carried out. However, if a transfer takes place between two locations within the same warehouse, the receipt activities are not carried out. You can use transfer orders to define a replenishment system within a single warehouse. This system controls replenishment from bulk locations to pick locations. Note: LN allows you to modify the outbound order line data based on the value the Allow Updating Outbound Order Lines up to and including field is set to in the Warehousing Order Types (whinh0110m000) session.

BPCS/LX Tip of the Day: LX Inventory Pallet Status Flow

Anthony Etzel 0 49972 Article rating: No rating

Four fields in the Item/Warehouse record (IIW file) affect the disposition of the

pallet status.

 

1.  Goods Receiving Code: You define these codes in Goods Receiving Maintenance (WHM130). The codes control whether or not the stock passes through inspection, what percentage, or quantity of a delivery to inspect, and the number of quarantine days, if any.

 

2.  Inspection Zone/Inspection Location: Either the Inspection Zone or the Inspection Location must be entered on the Item/Warehouse Master Maintenance screen WHM150D2-01.

 

First112113114115117119120121Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for EXECUTIVES

FINANCE: Use of Electronic Bank Statements

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

  1. Convert Electronic Bank Statements (tfcmg5202m000)
    Convert the received bank file to a format that LN can process. LN stores the converted bank statement files in the directory specified in the Path For EBS Archive field of the Bank Relations (tfcmg0510m000) session. In the Pathname EBS File field, you must add the file name. To add the current date to the file name, append a tilde (~) to the file name.

  2. Validate Bank Statements (tfcmg5202m000 / tfcmg5510m000 / tfcmg5511m000)
    Validate the converted electronic bank statement.

  3. Match Bank Statements (tfcmg5210m000)
    Automatically match as many of the imported statements (status Validated) as possible with open items. LN can match the statements with sales invoices, purchase invoices, and anticipated payment documents.

    Matching Options:

    • Match - Surplus on Aging / Unallocated (Default value)
    • Match - Surplus on Unallocated
    • Match - Surplus to be allocated Manually
    • Allow Underpayments
    • Use Payment Difference Tolerance
       
  4. Matching Results (tfcmg2500m100)
    Review the results of the matching process.

    To handle an unmatched amount, you can:

    • Manually add an unallocated payment or receipt line.
    • Reconcile the surplus with remaining open entries of the business partner.
       
  5. Post Bank Statements (tfcmg5210m100)
    Post the bank transactions to the General Ledger.

    Update the business partner’s bank account number and other details in the Bank Account by Pay-by Business Partner (tccom4115s000) session, based on the details read from the bank statement file.

OPERATIONS: What is Statistical Inventory Control (SIC) and How Does It Work?

Statistical Inventory Control (SIC) is an inventory-controlled order system designed to maintain stock levels based on predefined thresholds, rather than being demand-driven like EP (Enterprise Planning). Since SIC relies on inventory levels, it may lead to higher stock levels. To minimize financial risks, SIC is best suited for:

  • Low-cost items.
  • Items with predictable demand or short lead times.


Applications of SIC

  • Low-Cost Items: Particularly effective for inexpensive goods.
  • Predictable Demand or Short Lead Time: Suitable when demand patterns are stable or lead times are minimal.
  • Warehouse-Specific Planning: Useful for planning by warehouse rather than across the supply chain.
  • Trading Industries: Commonly employed in sectors like supermarkets.
  • Immediate Demands: Effective for items required immediately by customers.
  • Ease of Use: Simple to implement and manage.


Limitations of SIC

  • Does not account for dependent demand from planned orders (e.g., MPS/MRP/INV).
  • Does not generate distribution orders.
  • Ignores time-phased planned orders.
  • Lacks forecast consumption techniques.
  • Uses both nettable and non-nettable warehouses.

How SIC Works

SIC operates based on the Reorder PointStock Levels, and Order Method.

Triggering SIC

When Economic Stocks (calculated as On-Hand Inventory + On-Order – Allocated Stocks) on the Horizon Date fall below the Reorder Point, SIC triggers the creation of:

  • Planned Purchase Advice.
  • Planned Production Advice.


Order Methods in SIC

The quantity for these advices is determined by the Order Method, which can be one of the following:

  • Replenish to Maximum Stock
  • Fixed Order Quantity
  • Economic Order Quantity (EOQ)
  • Lot-for-Lot

Example: SIC in a Supermarket

Scenario: Managing stock for Ice Cream (1 Kg Pack)

  • Current Stock: 10 PCs
  • Reorder Point: 5 PCs
  • Safety Stock: 2 PCs
  • Lead Time: 1 Day
  • Order Method: Replenish to Maximum (Maximum Stock: 20 PCs)
  • Maximum Anticipated Consumption: 3 PCs/Day

Process:

  1. Customer purchases reduce the stock.
  2. When stock reaches 5 PCs, SIC is triggered.
  3. A Purchase Advice is generated for 15 PCs to replenish stock to the maximum level (20 PCs).
  4. During the lead time (1 day), the remaining 3 PCs (excluding Safety Stock) meet customer demands.
  5. In emergencies, Safety Stock can also be utilized.

Statistical Inventory Control offers a practical approach for managing inventory levels, particularly in industries with predictable demand or fast-moving items. However, its limitations make it less ideal for complex or time-phased planning scenarios.

TECHNOLOGY: Archiving Data from tipcs300 and ticst300 Tables

1. Archiving tipcs300

  • Using Session tipcs2260m000:
    • When archiving PCS projects, selecting the "Archive Financial data" option ensures that:
      • Records in tipcs300 are archived to the archiving company.
      • Records are deleted from the original company.
    • If records remain in tipcs300:
      • They may belong to projects that have not been archived.
      • The project may have been archived without selecting "Archive Financial data."
    • Verify there are no errors during the archiving process.
  • Using Session tipcs3500m001:
    • The session "Delete Financial Transactions by Project" can delete records from tipcs300.
    • Note: This session is not for archiving; it removes records without copying them to the archiving company.

2. Archiving ticst300

  • Using Session ticst0250m000:
    • The session "Archive Production Orders" allows:
      • Archiving and deleting records from the original company.
      • Only deleting records from the original company.
    • When executed:
      • Records in ticst300 associated with archived orders are removed.
      • Remaining records belong to unarchived orders.

Previous Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Archiving Data from tipcs300 and ticst300 Tables
Next Article Infor LN & Baan Tips & Tricks: Action Required - Infor LN Cloud Edition - Fonts Update!
Print
55909 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories