BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 62535 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 58265 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 66272 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 84296 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 58463 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 59750 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 28858 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 63532 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

First108109110111113115116117Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Year-End Processing Checklist for Period and Fiscal Year Closure

The conclusion of the fiscal year is inevitably a hectic period, making it crucial not to overlook essential tasks within your ERP system to ensure a seamless year-end close and set the stage for a successful start to the upcoming year. Below are critical items to include in your comprehensive checklist:

Year-End Close Process:

  1. Remove discontinued items.
  2. Eliminate sold purchase receipts.
  3. Clear lot attributes for sold lots.
  4. Update standard cost based on the current cost field (for environments without Manufacturing only).

Prepare for Year-End Close:

  1. Conduct a comprehensive physical inventory and update quantities before the actual year-end or establish a robust cycle-counting program.
  2. Review and post any applicable sales and purchase invoices/returns.
  3. Prepare users for a year-end push to complete all year-to-date inventory adjustments, receipts, and invoicing.
  4. Determine procedures for handling new year transactions without immediate posting.
  5. Establish new standard costs for the upcoming year (Manufacturing).
  6. Discuss cutoff dates for removing Archived BOMs and Closed/Canceled Mfg Orders (Manufacturing).

Finance Specific Items:

  1. Set up financial periods for 2024 (fiscal, reporting, and tax, as applicable).
  2. Open January period in 2024.
  3. Finalize any outstanding transactions from the current year (2023).
  4. Perform a soft-close for any open periods in 2023.

General Baan/LN Tips:

  1. Issue any pending old sales invoices.
  2. Resolve outstanding financial integration errors.
  3. Establish new integration mapping for 2024 as needed.
  4. Test the mapping in a controlled environment before the new year.
  5. Review and update jobs to ensure they will process in 2024.
  6. Determine, for cash-flow purposes, which purchase invoices won’t be paid until 2024.
  7. Verify that calendars are set up for the new year with holidays correctly indicated.
  8. Check jobs to ensure that any with hard-coded dates will point at the new year.

For additional insights and tips on year-end processing, refer to the relevant documents in the Infor Knowledge Base.

 KB 

 Content 

 1879191  

 Document including step by step procedure, possible error/warning messages, and more (Infor LN) 

 1147023 

 Step by step procedure description (Infor LN)

 1116239 

 Step by step procedure description (Infor LN)

 1117334

 Step by step procedure description (Infor LN; Portuguese)

 1171300 

 Step by step procedure description (Baan IV) 

If you require assistance or have any questions, feel free to reach out to us, and we'll gladly guide you through the necessary steps to ensure a thorough and accurate completion of your year-end processes. Contact us at 1.800.762.2077 or via email at solutions@crossroadsrmc.com. Your success is our priority, and we're here to help.

Previous Article Infor LN & Baan Tip: When is backflushing disabled in LN?
Next Article Infor LX / BPCS & Infor LN / Baan Tip: Time for the Notorious TRIO: Manual -  Physical -  Inventory
Print
60820 Rate this article:
2.5
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories