Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 55300 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 26286 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 50061 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 50654 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 50268 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items

Kathy Barthelt 0 63454 Article rating: 3.0

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

BPCS/LX Tip of the Week: Indirect Time Reporting

Anthony Etzel 0 48213 Article rating: No rating

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.

  • If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  • If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

Baan/LN Tip of the Week: Differences Between Constraint Planning in Baan IV and Enterprise Planning in LN

Kathy Barthelt 0 53608 Article rating: No rating

In Baan IV, a distinction is made between the actual ERP system and a separate planning tool which contains the Constraint Planning package. This tool was intended to work with any ERP system, not just with Baan IV. The Enterprise Planning package is now considered to be a package like any other package in Infor LN.

Users of Baan IV could choose whether they wanted to plan their supply in one of the following ways:

  • By using the MPS and MRP modules in the Manufacturing package.
  • By using the RPD and RMP modules in the Constraint Planning package.

Users of Infor LN can only use the Enterprise Planning package. The distinction between the MPS items and MRP items has been abandoned. In Infor LN, all items can be planned by using a combination of master-based planning methods and order-based planning methods.

First106107108109111113114115Last

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Year-End Processing Checklist for Period and Fiscal Year Closure

The conclusion of the fiscal year is inevitably a hectic period, making it crucial not to overlook essential tasks within your ERP system to ensure a seamless year-end close and set the stage for a successful start to the upcoming year. Below are critical items to include in your comprehensive checklist:

Year-End Close Process:

  1. Remove discontinued items.
  2. Eliminate sold purchase receipts.
  3. Clear lot attributes for sold lots.
  4. Update standard cost based on the current cost field (for environments without Manufacturing only).

Prepare for Year-End Close:

  1. Conduct a comprehensive physical inventory and update quantities before the actual year-end or establish a robust cycle-counting program.
  2. Review and post any applicable sales and purchase invoices/returns.
  3. Prepare users for a year-end push to complete all year-to-date inventory adjustments, receipts, and invoicing.
  4. Determine procedures for handling new year transactions without immediate posting.
  5. Establish new standard costs for the upcoming year (Manufacturing).
  6. Discuss cutoff dates for removing Archived BOMs and Closed/Canceled Mfg Orders (Manufacturing).

Finance Specific Items:

  1. Set up financial periods for 2024 (fiscal, reporting, and tax, as applicable).
  2. Open January period in 2024.
  3. Finalize any outstanding transactions from the current year (2023).
  4. Perform a soft-close for any open periods in 2023.

General Baan/LN Tips:

  1. Issue any pending old sales invoices.
  2. Resolve outstanding financial integration errors.
  3. Establish new integration mapping for 2024 as needed.
  4. Test the mapping in a controlled environment before the new year.
  5. Review and update jobs to ensure they will process in 2024.
  6. Determine, for cash-flow purposes, which purchase invoices won’t be paid until 2024.
  7. Verify that calendars are set up for the new year with holidays correctly indicated.
  8. Check jobs to ensure that any with hard-coded dates will point at the new year.

For additional insights and tips on year-end processing, refer to the relevant documents in the Infor Knowledge Base.

 KB 

 Content 

 1879191  

 Document including step by step procedure, possible error/warning messages, and more (Infor LN) 

 1147023 

 Step by step procedure description (Infor LN)

 1116239 

 Step by step procedure description (Infor LN)

 1117334

 Step by step procedure description (Infor LN; Portuguese)

 1171300 

 Step by step procedure description (Baan IV) 

If you require assistance or have any questions, feel free to reach out to us, and we'll gladly guide you through the necessary steps to ensure a thorough and accurate completion of your year-end processes. Contact us at 1.800.762.2077 or via email at solutions@crossroadsrmc.com. Your success is our priority, and we're here to help.

Previous Article Infor LN & Baan Tip: When is backflushing disabled in LN?
Next Article Infor LX / BPCS & Infor LN / Baan Tip: Time for the Notorious TRIO: Manual -  Physical -  Inventory
Print
38698 Rate this article:
2.5
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories