Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Crossroads RMC Data Collection: Roslyn Converters is on a Roll!

Crossroads RMC 0 30337 Article rating: 5.0

Roslyn Converters, a leading producer of specialized paper for the food, tobacco, pharma and retail industries, has selected Crossroads RMC’s data collection solution for Baan as part of a system wide upgrade of their existing internal systems and software. As part of this project, Roslyn will be installing the latest version of the Crossroads RMC Data Collection Software for Baan, and will be moving to a current version of Honeywell data collection hardware. The project will kick off this month, and is expected to go live within the next 30 days.

Lunch & Learn Webinar for BPCS & LX

The Secret to Making Plans Happen

Anthony Etzel 0 29449 Article rating: 5.0


Lunch & Learn Webinar for BPCS & LX! 
- The Secret to Making Plans Happen -

Your business doesn’t run without the right people and processes in place, but in order for people to manage the right things at the right time, they need tools... the RIGHT tools. 

The secret to making plans happen is using a tool that improves the effectiveness of buyers, planners, schedulers, and supervisors. The secret is OTTO.

Learn about how OTTO can benefit your business and make YOUR plans happen.

Did you miss the webinar? Click below to watch the recording.

Tip of the Week: 10 Ways to Succeed at an OEE Project Where 90% Fail

Kathy Barthelt 0 110106 Article rating: No rating
  1. Collect the requirements. Learn from everyone with the intent of developing a phased approach to implementing on your shop floor with OEE being Phase 1. 
  2. Create your list. Capture all of required functions, taking into account what the “output” of the system will be. What does the plant manager need to see in real-time? What KPI’s does each line need displayed in real-time? What reports are required?
  3. Insist Upon Real-time. In the moment data for the right OEE is the right approach. If it’s possible, collect the data automatically. Remember that real-time feedback to line operators results in an automatic increase in OEE.
  4. Evaluate your lines. Focus where production counts can be monitored automatically. If the data is in your PLC’s, can you get it out? OPC communication is the right way to go here. If not, the approach is to install a new dedicated PLC with sensors installed on each line.

BPCS/LX Tip of the Week: 5 Ways to Motivate Your Employees

Anthony Etzel 0 52709 Article rating: 5.0

Here are 5 ways you can motivate your employees to give their best every day:

1. Train Your Employees

2. Give Your Employees the Right Tools

3. Automate Processes

4. Give Your Employees Real-Time Feedback

5. Provide Incentives to Do More

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees

Kathy Barthelt 0 82363 Article rating: No rating

Here are 5 ways you can motivate your employees to give their best every day:

1. Train Your Employees

2. Give Your Employees the Right Tools

3. Automate Processes

4. Give Your Employees Real-Time Feedback

5. Provide Incentives to Do More

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Anthony Etzel 0 55993 Article rating: 5.0

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: How is Your Productivity?

Kathy Barthelt 0 81115 Article rating: No rating

Are your employees not as productive as you’d like them to be? Are jobs not getting completed on schedule? 

Without actual data, making decisions about how efficient your operation is will be difficult. Start tracking actual time to complete each operation. Compare different production lines running the same job. Is one line running more efficiently? If so, start looking at why. Track downtime, setup, etc. Once you start really analyzing each piece of the puzzle, you can begin to uncover areas that are ripe for improvement.

Optimize Your Manufacturing Today!

Tip of the Week: Create a Repeatable Process

Kathy Barthelt 0 100543 Article rating: No rating

If you’ve been successful doing something in the past, you want to keep doing it that way. Are your procedures documented? Do you have workflows defined? Would creating video tutorials be helpful, especially for new employees? Giving employees the tools to be successful helps to ensure the success of the business as a whole.

Optimize Your Manufacturing Today!

First8586878890929394Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Next Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Print
33073 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories