Tip of the Week: 10 Ways to Succeed at an OEE Project Where 90% Fail

Kathy Barthelt 0 106010 Article rating: No rating
  1. Collect the requirements. Learn from everyone with the intent of developing a phased approach to implementing on your shop floor with OEE being Phase 1. 
  2. Create your list. Capture all of required functions, taking into account what the “output” of the system will be. What does the plant manager need to see in real-time? What KPI’s does each line need displayed in real-time? What reports are required?
  3. Insist Upon Real-time. In the moment data for the right OEE is the right approach. If it’s possible, collect the data automatically. Remember that real-time feedback to line operators results in an automatic increase in OEE.
  4. Evaluate your lines. Focus where production counts can be monitored automatically. If the data is in your PLC’s, can you get it out? OPC communication is the right way to go here. If not, the approach is to install a new dedicated PLC with sensors installed on each line.

BPCS/LX Tip of the Week: 5 Ways to Motivate Your Employees

Anthony Etzel 0 50663 Article rating: 5.0

Here are 5 ways you can motivate your employees to give their best every day:

1. Train Your Employees

2. Give Your Employees the Right Tools

3. Automate Processes

4. Give Your Employees Real-Time Feedback

5. Provide Incentives to Do More

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees

Kathy Barthelt 0 80193 Article rating: No rating

Here are 5 ways you can motivate your employees to give their best every day:

1. Train Your Employees

2. Give Your Employees the Right Tools

3. Automate Processes

4. Give Your Employees Real-Time Feedback

5. Provide Incentives to Do More

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Anthony Etzel 0 54356 Article rating: 5.0

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: How is Your Productivity?

Kathy Barthelt 0 79172 Article rating: No rating

Are your employees not as productive as you’d like them to be? Are jobs not getting completed on schedule? 

Without actual data, making decisions about how efficient your operation is will be difficult. Start tracking actual time to complete each operation. Compare different production lines running the same job. Is one line running more efficiently? If so, start looking at why. Track downtime, setup, etc. Once you start really analyzing each piece of the puzzle, you can begin to uncover areas that are ripe for improvement.

Optimize Your Manufacturing Today!

Tip of the Week: Create a Repeatable Process

Kathy Barthelt 0 96860 Article rating: No rating

If you’ve been successful doing something in the past, you want to keep doing it that way. Are your procedures documented? Do you have workflows defined? Would creating video tutorials be helpful, especially for new employees? Giving employees the tools to be successful helps to ensure the success of the business as a whole.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: 6 Powerful Steps to Win With Automation

Anthony Etzel 0 51622 Article rating: 5.0
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.     
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: 6 Powerful Steps to Win With Automation

Kathy Barthelt 0 80080 Article rating: No rating
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.    
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

First7778798082848586Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan FINANCE Tip: Is it possible to upload accounts receivable invoices into LN using Excel?

Yes, this is possible, by following the steps below:

1. Maintain a batch

2. Maintain an invoice headerexport it, add an additional invoice header to the Excel file, and import it

3. Maintain an invoice line for the first invoice, export it, add additional invoice lines to the Excel file and import it
 

Below the above steps are described in detail.

1a. Open the transactions (tfgld1101m000) session and create a batch.

1b. Insert a transaction type, used for creating sales invoices, like ACR, and open it.

2a. The Sales Invoices (tfacr1110s000) session starts. Maintain the invoice header and save it. For example sales invoice ACR 4497.

2b. In the Actions menu select Export and Import -> Advanced Export (fields: All tabs).

2c. In the excel file created during previous step, add the headers for the invoices to be uploaded. Notice if for the transaction type the Documents in Fixed Sequence checkbox is ticked in the Transaction Types (tfgld0511m000) session, the document number for the not-yet existing invoices to be imported in LN should be equal to the default series for this transaction type. Otherwise, so if the Documents in Fixed Sequence checkbox is not ticked, the desired document numbers can be maintained in the excel file.

2d. In the Sales Invoices (tfacr1110s000) session in the Actions menu select Export and Import -> Settings, and make sure the Import Only in This View checkbox is NOT ticked. Then select in the Actions menu select Export and Import -> Import, select the excel file as saved in the prior step, and import it. Afterwards the invoice headers should be visible in the Sales Invoices (tfacr1110s000) session.

3a. Navigate to the first invoice, select Lines. The Transactions (tfgld1102m300) session opens. Maintain at least 1 line and save it.

3b. Open the line created in the prior step. Notice the detailed version of the Transactions (tfgld1102m300) session opens.

3c. In the Actions menu select Export and Import -> Advanced Export (fields: All tabs).

3d. In the excel file created during previous step, add lines for the header invoice numbers as available in the Sales Invoices (tfacr1110s000) session (as per step 2d).

3e. In the detailed version of the Transactions (tfgld1102m300) session in the Actions menu select Export and Import -> Import, select the excel file as saved in the prior step, and import it.

Previous Article Infor LN / Baan Tips & Tricks for EXECUTIVES
Next Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Print
22077 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories