Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?

Kathy Barthelt 0 49973 Article rating: 5.0

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Infor LX / BPCS Tips & Tricks for Finance: Inventory Period Balance Freeze

George Moroses 0 18031 Article rating: 5.0

Users can now freeze period-end balances at the end of a fiscal period. You can now store the opening/ending on hand balance for each Inventory period at the Item (IIM), Warehouse/Item (IWI) and Lot/Location (ILI) levels. This information can then be used for inventory tracking and valuation purposes, as well as other ad hoc financial and audit reporting requirements. Infor LX clients can backdate inventory transactions into the immediate previously closed period, and thus update what was saved as the opening/ending balance throughout the current open period.

Infor LX / BPCS Tips & Tricks for Operations: Retain Lot Status on Shipped Resupply Orders

George Moroses 0 13082 Article rating: 5.0

When a lot is completely shipped on a customer order, the Lot Status is changed to Z. Since a resupply order must still be received in the To Warehouse to complete the transaction, do not update the lot status when the resupply order is shipped. If a lot is completely shipped on a resupply order, LX no longer updates the lot status to Z, because the shipped lot retains its current lot status, the additional steps, no additional steps are required to receive it in the To Warehouse.

Infor LX / BPCS Tips & Tricks for Technology: Reset Purchase Order In Use

George Moroses 0 13985 Article rating: 5.0

This feature resolves or resets a purchase order or requisition that is no longer being processed, but the system still indicates it is 'in use'. The user selects Purchase Order/Requisition in Use Maintenance, PUR940D, from the Purchasing Management Menu, PUR, located in the Special Processing sub-menu. The user then enters an order or requisition to remove the 'In Use' status.

End of Year E R P Checklist: Streamline Your Transition to the New Year

Crossroads RMC 0 7014 Article rating: 5.0

The end of the year is a busy time for everyone, but a little preparation can make the start of the next year smoother and more productive. Here's a checklist broken out by the department to help optimize your ERP system as you wrap up this year.

  1. All Departments Checklist
  2. Technology Checklist
  3. Operations Checklist
  4. Finance Checklist
First34568101112Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Infor LN & Baan Tip of the Week: Reports to Analyze Company Performance

You know what data you need to analyze your company’s financial and production health, but sometimes it's a struggle to get that data in a format that is meaningful. Here are some reports in Baan IV, Baan V, and Infor LN which you may find useful.

As is the case with most ERP reports, with each version progression from Baan IV, to Baan V, to LN, there are improvements in selection criteria and report content. Some may require some setup and others may require some formatting if you would like to export them to Excel.  Contact me if you have questions or need assistance.

BAAN & LN FINANCE:

Baan IV –

Customer Statistics Module

  • Print Customer Statistics by Customer/Credit Analyst (tfcmg3400m000)
    • Prints Average Days Payment, Amount Paid, Average Days Outstanding, Amount Open, Discounts Allowed and Discounts Taken.  
       
  • Print Average Days Outstanding (tfcmg3401m000)
    • Prints Open Amount and Average Days Outstanding.
  • Print Average Receipt Days (tfcmg3402m000)
    • Prints Amount Paid and Average Number of Days for a Payment.


Cash Forecasting Module

  • Print Cash Forecast Summary by Period/Currency (tfcmg3410m000)
    • Prints Total Cash coming in from Sales Invoices, Sales Orders, Sales Quotes, Project Orders, and Budgets. Prints Total Cash going out from Purchase Invoices, Purchase Orders, Standing Orders, and Budgets.
       
  • Print Cash Forecast Summary by Date/Currency (tfcmg3411m000)
    • Prints the same as above but by a specific date.
       
  • Print Cash Forecast Details by Period/Currency (tfcmg3412m000)
    • Prints the same as above but by each period across in columns.
       
  • Prints Detailed Cash Forecast in Home Currency (tfcmg3413m000)
    • Prints each item, purchase order, sales order, etc, with forecast in home currency.


Baan V –

  • Print Finalized Transactions Ledger Account – tfgld1406m000
    • Output can be run to show transactions (debit/credit) by ledger account, transaction type, and time periods. This can be run by range of ledger account and/or range of periods.
  • Print Integration Transactions -tfgld4410m000
    • This has 3 options: a short version of the report, a standard version, and a version by company/ledger account.

Infor LN -

  • Print Finalized Transactions Ledger Account – tfgld1406m000
    • Output can be run to show transactions (debit/credit) by ledger account, transaction type, and time periods. This can be run by range of ledger account and/or range of periods.
  • Print Integration Transactions by Business Flow – tfgld4482m100
    • Output can be run to show all transactions (debit/credit) by business object (production/purchasing/sales)


BAAN & LN MANUFACTURING:

Baan IV

  • Print Actual Cost by Production Order ticst0401m000
    • This report can be run at any time in the production order’s life to show how hours-spent and material-used compare between estimated and actual usage.
       
  • Print Work Center Utilization By Week tiscf1402m000
    • This report shows capacity issues at work centers/machines which help identify production bottlenecks.


Baan V

  • Print Estimated vs Actual Material Costs ticst0401m000
    • This report can be run at any time in the production order’s life to show how actual material-used compares to estimated usage.
       
  • Print Estimated vs Actual Hour Costs ticst0402m000
    • This report can be run at any time in the production order’s life to show how actual hours-spent compares estimated hours.
       
  • Print Work Center Utilization By Week tiscf1402m000
    • This report shows capacity issues at work centers/machines which help identify production bottlenecks.


Infor LN

  • Print Estimated vs Actual Material Costs ticst0401m000
    • This report can be run at any time in the production order’s life to show how actual material-used compares to estimated usage.
       
  • Print Estimated vs Actual Hour Costs ticst0402m000
    • This report can be run at any time in the production order’s life to show how actual hours-spent compares estimated hours.
       
  • Utilization report from– Print Resource Order Plan cprrp0430m000
    • This report from Enterprise Planning will show all orders from planning and production. By incorporating both order types, capacity issues can be seen short range where planning has determined that new orders are needed, as well as long range where planners may find opportunities to shift work or even to plan machine maintenance.

Previous Article The Best Baan | Infor LN Manufacturing Reports to Analyze Company Performance
Next Article Infor LN & Baan Tip of the Week: Year End
Print
66147 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories