OTTO: Making plans happen isn’t just about monitoring material shortages

George Moroses 0 28101 Article rating: 5.0

Making plans happen isn’t just about monitoring material shortages. Supporting activities can be the real cause of delays. Some non-material events customers have monitored using OTTO include:

  • Scheduling and coordination of outside services (such as heat treating and plating)
  • Quality Assurance for pharmaceuticals and inspection
  • Moving off-site inventory to the plant
  • Moving inventory from temporary (conveyor) location to pickable location
  • Scheduling of overseas containers
  • Design engineering for make-to-order

OTTO provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time.

Visit Our OTTO page to learn more.

How Do I Determine If MES Is Right For My Business?

George Moroses 0 30270 Article rating: No rating

There are certain key questions that must be answered to determine whether or not an MES system would benefit your organization: 

  • How do you analyze OEE?
  • Is there an opportunity to reduce WIP inventory, indirect labor, downtime, waste or scrap?
  • What is the cost and impact of producing and distributing shop paper including drawings and work instructions?
  • Would you like to go paperless on your shop floor?
  • How are your continuous improvement initiatives tied to your ERP?
  • Is Management requesting real time production status reporting via dashboards or drilldown reports?
  • What different “islands of automation” exist on your shop floor?

The answers to each of these questions could have a significant impact on the profitability of your business. Want to quantify your results? Contact George Moroses today to schedule your FREE MES ROI Analysis.

Consulting: Methodology for Infor LX & BPCS Upgrades

Anthony Etzel 0 40158 Article rating: 5.0

Throughout the years, Crossroads RMC has participated in several 4.0.05CD upgrades to LX, from which we had the opportunity to refine our methodology for CEA (Configurable Enterprise Accounting) implementations/upgrades. As a result, we have fine tuned our overall upgrade approach and have been very successful in implementing this approach with our clients.

CEA replaces the green screen GLD module and allows for considerable flexibility in the design of the COA (Chart of Accounts).

Our approach incorporates any changes that are needed in the COA and facilitates the transfer or replacement of Profit Centers and Account Codes from BPCS to LX, building on the existing GL. Among the issues we manage is the conversion of historical GL balances.

We maximize the use of LX and CEA while minimizing the manual effort that gets you there.

Contact Frank Petrasio to discuss how we can help you:

  • Preserve what works in BPCS
  • Optimize what works in LX

with a maximum of respect for your time and budget. Learn more about Crossroads RMC Consulting>

Infor LX & BPCS Tip of the Week: Additional Selection Criteria for Cycle Count Purge Enhancement – 8.4

Anthony Etzel 0 57852 Article rating: 5.0

The final step in Cycle Count processing is to maintain the (ICY) Cycle Count file. This history file increases in size with each posting session. It is up to users to purge the historical data that you no longer need. Previously, INV015 Cycle Count Purge by date only allowed users to purge the cycle count file by date. Now, additional selection criteria have been added that allows users improved ways to control records they may want to purge.

Infor LN & Baan Data Collection News: Crossroads RMC Cycle Counting Application

Kathy Barthelt 0 35069 Article rating: 5.0

How often are you counting your inventory? Are you sure your counts are accurate?  Are inaccurate counts affecting your ability to satisfy customer orders?

Crossroads RMC Cycle Counting Application gives you:

· Overall increased inventory accuracy

· Ability to review and approve count before direct update of Baan/LN tables

· Elimination of unnecessary re-orders of items with current inventory

· Greater ability to satisfy customer orders due to greater visibility to (accurate) inventory levels

· Direct labor cost savings – less staff required for count

· Increased productivity during count – with some of our customers, counts used to take weeks. They can now complete a count of all their inventory in one day.

Learn more: Crossroads RMC Data Collection - Web Collect 

Consulting News: ERP Implementation or Upgrade... Are You Prepared?

Crossroads RMC 0 38968 Article rating: 5.0

There are several factors that need to be considered when undertaking a major project like an ERP implementation or upgrade. Before you look to others outside of your organization to provide the expertise needed, you need to first look internally to ensure that the right players are in place to lead the project and also ensure business continuity during the project.

  • Executive Sponsorship - Does Senior Management have a clear and well understood commitment to project success?
  • Strong Project Manager?
  • Core Team Functional Representation - Are the Team Members knowledgeable participants and able to keep the project moving forward?
  • User Community Support?
  • Motivation - Are the Team Members willing and able to provide the time needed for a large-scale implementation?

Do You need help figuring out if your organization is properly positioned for an implementation or upgrade? Contact us. We can help.

Infor LN & Baan Tip of the Week: Job Shop Bill of Material – 10.7

Kathy Barthelt 0 78289 Article rating: 5.0

The job shop bill of material is defined by site. It is used as the source for the estimated materials in the job shop production order.

The new job shop bill of material differs from the old bill of material. These changes are applicable for the new job shop bill of material:

  • It has a header and a status.
  • It is always revision controlled.
  • It can be designated for planning and for costing.
  • The effective dates have been moved from the material lines to the header.
  • The BOM quantity has been moved from item production data to the header.
  • The use up has been moved from alternatives to the material line.
  • The warehouse is defined on the material line (mandatory).
  • The routing operation is defined on the material line (optional).

The job shop bill of material can be generated through the production bill of material.

IDF News: default order class for the warehouse customer

George Moroses 0 29780 Article rating: 5.0

In IDF Customers, the default order class for the warehouse customer should be a user-defined order class (base order class = 004). Do not use base order class 002 or 005, to allow for automatic invoicing of warehouse orders (if a separate manual Ship Confirm event is required per the order class, auto invoicing cannot occur from Pick Confirm).

First6465666769717273Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Harnessing the Power of AI to Help Manufacturers Sell More at the Right Time

AI: Transforming Manufacturing—From Production to Profitability

As AI reshapes industries, manufacturers ask critical questions: How will customers discover and purchase products in an AI-driven world? And how can companies keep pace with these advancements?

At Crossroads RMC, we address these challenges with our AI Readiness Assessment (AIRA). An AIRA creates a clear, actionable digital roadmap, significantly boosting efficiency, accuracy, and strategic capabilities. This assessment ensures a smooth, swift AI transition.

AI Readiness Assessment targets key Financial areas:

  • Cash Flow Management: AI improves cash flow forecasting, identifying potential shortfalls before they impact operations.

  • Cost Control: By analyzing spending patterns, AI reveals areas for cost reduction; maintaining quality and efficiency.

  • Financial Forecasting: AI uses historical data and market trends to enhance forecasting accuracy, empowering strategic financial decisions.

AI Readiness Assessment targets key Operations areas:

  • Production Planning: AI optimizes production planning by analyzing data and forecasting demand, helping to balance workloads and minimize downtime.
  • Supply Chain Disruptions: AI predicts potential disruptions and suggests alternative suppliers or routes, enhancing supply chain resilience.
  • Quality Control: AI detects defects in real-time and predicts quality issues before they occur, leading to higher consistency and fewer recalls.


AI Readiness Assessment targets key Technology areas:

  • Data Management: AI organizes, analyzes, and develops actionable insights from data.
  • Security and Compliance: AI enhances cybersecurity measures by detecting anomalies and potential threats in real-time, and automates compliance checks to ensure adherence to regulatory standards.
  • Performance Monitoring: AI continuously monitors system performance and identifies areas for improvement, ensuring optimal operation.
     

AI Readiness Assessment target key Executive areas:

  • Operational Visibility: AI integrates data from various sources to provide real-time visibility into all aspects of the business, enhancing oversight and control.
  • Risk Management: AI analyzes market trends, supply chain data, and internal processes to identify potential risks and recommend mitigation strategies.
  • Market Competitiveness: AI provides insights into market trends, customer preferences, and competitor activities, helping executives stay ahead of the curve.

How the Crossroads/Aleran can help you modernize your business through the use of AI (27:36)

Watch our video to learn more!

Connect with us at 800.762.2077, solutions@crossroadsrmc.com, or request an AI Readiness Assessment to start your path towards a flexible, future-proof ERP.
 

Print
12505 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

x

Categories