BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 81163 Article rating: No rating

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Crossroads MES Version 11 Released

Anthony Etzel 0 55053 Article rating: No rating

Crossroads MES Version 11 was rolled out in March, 2014. Some of the new features include a new GUI interface, improved End of Shift review functions, pre-formatted production label printing, and an electronic shop packet on the factory worker Job In screen.

Crossroads MES Released for Tablet

Anthony Etzel 0 51135 Article rating: 3.7

Crossroads RMC announces that the Crossroads MES solution is now compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

First130131132133134135136137139

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES:
Next Article Infor LN & Baan Tips & Tricks for Technology: Using audit files in the Exchange module
Print
53554 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories