Baan/LN Tip of the Week: Company Calendar

Kathy Barthelt 0 74483 Article rating: No rating

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: SFC600 & SFC650

Anthony Etzel 0 86775 Article rating: No rating

These programs are used to capture and post shop floor information. Labor reporting, machine time, etc. can be captured by either program. The key difference is that one will also capture the production receipt and backflush components. Based on your company information / transaction process, one of these programs will most likely be used daily to capture current shop floor data. You can use the shop packet labor ticket for the manual recording, and the keying of the data. Alternatively, you can incorporate an automated method like an MES solution to capture the data and streamline the process.

Crossroads RMC to Exhibit at Manufacturing Matchmaking 2014

Crossroads RMC 0 45033 Article rating: No rating
Crossroads RMC will exhibit at the inaugural Illinois Manufacturing Excellence Center (IMEC) Manufacturing Matchmaking Event 2014 on September 23, 2014. Manufacturers from across the state of Illinois will come together at this event to discuss ways to improve the productivity and competitiveness of Illinois' small and mid-sized manufacturing firms.

BPCS/LX Tip of the Week: What is the bubble number and how do I maintain it?

Anthony Etzel 0 78916 Article rating: No rating

The bubble number is maintained at the component level for each component defined on the Bill of Material. It is an extra user-defined reference number that you can use to re-sequence the maintenance screen display or bills of material listings.

In Infor LX, the system displays the bubble number for the existing child items. Engineering drawings often use a bubble number at the component level on the drawing so that same bubble number can be used on the Bill of Material for a link of the component to the drawing. Alternatively, you may use it simply as a method to sequence the BOM.

Be careful of how you assign the number. It is a good idea to assign the number with a consecutive count by 10 leaving room to allow for component additions to the Bill of Material.

Baan/LN Tip of the Week: Setting Up New Employees in LN

Kathy Barthelt 0 75002 Article rating: No rating

In LN, the People package is used to register the employee’s hours and expenses. To support the People package, the Employees - General (tccom0101m000) session only contains the general employee data.

The title of the Employees - General (tccom0101m000) session was changed to Employees – General (tccom0101m000).

From the Employees - General (tccom0101m000) session, users can start the following sessions to define the more specific employee data:

  • Employees - People (bpmdm0101m000).
  • Employees - Project (tppdm8101m000).
  • Employees - Service (tsmdm1140m000).
  • Skills by Employee (tcppl0120m000).
  • Employees by Team (tcppl0150m000).
  • Roles by Employee (tcppl0170m000).

After users define the employees, users can also start the listed sessions from the Employees Dashboard (bpmdm0101m100) session in People.

Baan/LN Tip of the Week: Month End - Miscellaneous To-Do's

Kathy Barthelt 0 71905 Article rating: No rating
  • Print Sales Order History Information
    • all invoices processed through sales
  • Check Inventory Valuation
    • this should tie out to your inventory accounts
  • Print Integration Information
    • see all postings from WIP to finished goods
  • Print G/L Transaction Information
    • print specific transaction types for any GL account
  • Print Lot Control Information
    • will show where serial numbers were used

BPCS/LX Tip of the Week: Why Define Location Fields in the Work Center File

Anthony Etzel 0 73908 Article rating: No rating

If you setup the “From” and “To” Location fields in the Work Center file, this will determine the locations for material issue transactions and production reporting transactions.

The reporting of the transactions happen through production reporting, JIT600, or using the Shop Floor labor posting, SFC600, or Shop Floor Posting from SFC650.

Remember, any location used in the work center file must first be set up in the location master file. Using an MES solution by-passes the need to key any of the data to Infor LX.

If ERP is plumbing for the Enterprise; How do we unplug it and keep it from making a huge mess?

David Dickson 0 55625 Article rating: 5.0

I have been working with ERP in various roles for over 30 years, directly involved in over a hundred implementations, while my company has been involved with over 300 more. Of course, in many ways the systems we use today are completely different from what we used in the ‘80s – back then it was green screens, simple transaction entry forms, and cumbersome updates (at best) to link what one department did with all the other areas that needed access to that information. Then there were those planning programs that took all the information along with various parameters the users needed to set and told us what to do.

The More Things Change, the More They Stay the Same

First120121122123124125127129

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Project Status Options

Ever wonder what the implications are of choosing one project status versus another?

Here is the explanation of project status possible values:

Free
You can carry out project engineering. This means that you can:

  • Define the project master schedule (PMS) by using the Project Control module.
  • Maintain the project structure.
  • Maintain the customized product structure by using customized bills of material and routing sheets.
  • Carry out project estimating.

Simulated
You simulate the rough capacity requirements planning and the detailed material and resource requirements planning (RRP) based on the network planning. The capacity requirements for a simulated project are visualized separately. Infor LN (ERP LN) generates planned RRP purchase orders, planned production orders, and PRP warehouse orders for customized items. However, those orders cannot be released. Moreover, the RRP does not allocate standard items to the project.

Active
This status indicates the project's execution stage. You can release planned orders so that the required purchase and production activities can be actually started and completed.

Canceled
The project has been canceled. You cannot release new orders for the project, but you can, however, finish pending logistical activities. You can close a canceled project, but a project can also remain canceled. If the project remains canceled, be aware that the final costs are not posted to Financials, and that WIP can still exist for completed orders. Costs are only posted if you close the project.

Finished
As far as manufacturing is concerned, the project is finished. Also, all purchase and production activities have been completed or closed, and all sales orders have been delivered for the project.

Closed
Financially, the project has been closed. This means that the financial project results have been computed. Financial project transactions can no longer be posted to the project.

To be Closed
If you select the COGS and Revenues restricted to Financial Company of PCS Project check box in the Project Control Parameters (tipcs0100m000) session, financial transactions are posted on the financial companies of the sales office, service department, and/or warehouse instead of on the financial company of the PCS project. If internal invoices are sent from the PCS project to those departments, and the internal invoices are not completed yet, the Close Project (tipcs2250m000) session sets the project status to To be Closed instead of to Closed. You must first complete the internal invoices, and then run the Close Project (tipcs2250m000) session again to set the project status to Closed.

Archived
The project has been archived. This means that all project data has been stored in archive files and is removed from the original files.

Previous Article Infor LN & Baan Tip: LN Order Management - Generating Purchase Receipts
Next Article Infor LN & Baan Tip: Cost Component Setup