Baan/LN Tip of the Week: What could go wrong with GRINYA?

Kathy Barthelt 0 77505 Article rating: No rating
One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan/LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error. It is recommended that the Integrations Setup tables be audited either through Baan or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Baan/LN Tip of the Week: Differentiating An Item By Supplier - LN

Kathy Barthelt 0 77276 Article rating: No rating

In LN, you can differentiate between items at various suppliers:

  • Locations (warehouses),
  • Purpose (planning, purchase)
  • Origin (supplier, warehouse)

Example

An item is supplied by two different suppliers. Supplier A ships in lots of 100 pieces due to how the item is packed. Supplier B ships the goods in units of 60 pieces.

You can define specific parameters for each supplier. The following sessions can be used to define these characteristics:
 
  • Items - Planning (cprpd1100m000)
  • Check Item Data by Warehouse (whwmd2210m000)
  • Item Supplier Plan (cpvmi0530m000)
These sessions define entities that have an n-to-1 relationship with the general item data.

 

BPCS/LX Tip of the Week: Inventory Control

Anthony Etzel 0 88816 Article rating: No rating

In Infor LX you need to determine how inventory will be moved in and out of warehouse storage locations, and which of the following transactions to use for inventory control:


  • A transfer transaction can be used to move inventory from one warehouse location to another warehouse location.
  • A production receipt transaction is used to add inventory to a warehouse location.
  • A material issue or backflush is used to reduce inventory from a warehouse location.

New Definition of Insanity: Collect data the same old way

Anthony Etzel 0 90671 Article rating: 5.0

Just because you've always done it this way doesn't mean it's the best way. The old way of doing things may get the job done, but is the job being performed efficiently, accurately, and on a timely basis?

People resist change because there is an element of fear behind change and having to learn something new. Sometimes it’s just that you’re comfortable with how things are done, and you don’t see the need to make any changes. 


Are you stuck in manual?

Improve Profit and Cut Costs at the Same Time

Crossroads RMC 0 41402 Article rating: No rating

Want to Improve Profit and Cut Costs at the Same Time?

“Real-time executives averaged a 14% improvement in operating cash flow and achieved a 6% reduction in operating costs” According to the Aberdeen Group.

So, how do you accomplish this great feat? By streaming real-time data to the executives.

The need for visibility into what is happening in the trenches, and the comprehensive understanding of key metrics and their implications for overall performance, are critical for an organization to be at the “top of their game”.   read full article>

Learn how Crossroads RMC can provide for this data streaming with Analytics Dashboards.

Industry News: How Small and Mid-Sized Manufacturers Can Harness the Transformative Power of Technology…

Crossroads RMC 0 45167 Article rating: No rating

Industry-Specific Technology Changes the Game:

"One of the most significant changes has been the development of software and enterprise-wide technology that is designed to specifically meet the needs of particular industries. This has multiple advantages. The technology doesn’t have to be “over-configured” to be functional; the functionality is built-in. It can also be deployed quickly and cost-effectively, with less effort and less risk." Industry Week Article by Kelly McGowan, American Securities.

 

Crossroads RMC has software that has been built specifically for your industry. Learn how Analytics Dashboard can improve your efficiency, productivity, and quality while driving down costs.

Industry News: Technology - The Secret Life of the American Factory

Crossroads RMC 0 43600 Article rating: No rating

New Data: New Fruit…that’s the promise of finding new data sitting right there under your nose on the factory floor.

Doug Woods, president of the Association for Manufacturing Technology and MTConnect champion says it this way:
"At the end of the day," he explains, "after you've invested in hardware and machines, at some point it all comes down to how do you wring the maximum amount of productivity out of them? How do you get the ultimate efficiency out of the facility?" The only way to be confident you're doing that, he says, is to really understand what is going on with all of the equipment in the factory all of the time. And that, he says, comes down to having "really good data." 

Read Full Article>

Discover How Crossroads RMC can meet this need with Analytics Dashboard.

Baan/LN Tip of the Week: Project Templates

Kathy Barthelt 0 82578 Article rating: No rating

Project templates are useful because you can specify all of the information that you would normally want to include when creating a new project such as project structure, budget, and so on.

In Baan IV/V, project templates do not exist, but you can set up a project template by creating a regular project, and setting the status to simulated or free. This is done so that the project does not create plans. Under this scenario, you can easily copy one project to another.

In LN, when you create a new project, a template can be used as the starting point. This is similar to copying a normal project, but unlike normal projects, no costs or revenues can be posted on a template.

First119120121122124126127128Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Project Status Options

Ever wonder what the implications are of choosing one project status versus another?

Here is the explanation of project status possible values:

Free
You can carry out project engineering. This means that you can:

  • Define the project master schedule (PMS) by using the Project Control module.
  • Maintain the project structure.
  • Maintain the customized product structure by using customized bills of material and routing sheets.
  • Carry out project estimating.

Simulated
You simulate the rough capacity requirements planning and the detailed material and resource requirements planning (RRP) based on the network planning. The capacity requirements for a simulated project are visualized separately. Infor LN (ERP LN) generates planned RRP purchase orders, planned production orders, and PRP warehouse orders for customized items. However, those orders cannot be released. Moreover, the RRP does not allocate standard items to the project.

Active
This status indicates the project's execution stage. You can release planned orders so that the required purchase and production activities can be actually started and completed.

Canceled
The project has been canceled. You cannot release new orders for the project, but you can, however, finish pending logistical activities. You can close a canceled project, but a project can also remain canceled. If the project remains canceled, be aware that the final costs are not posted to Financials, and that WIP can still exist for completed orders. Costs are only posted if you close the project.

Finished
As far as manufacturing is concerned, the project is finished. Also, all purchase and production activities have been completed or closed, and all sales orders have been delivered for the project.

Closed
Financially, the project has been closed. This means that the financial project results have been computed. Financial project transactions can no longer be posted to the project.

To be Closed
If you select the COGS and Revenues restricted to Financial Company of PCS Project check box in the Project Control Parameters (tipcs0100m000) session, financial transactions are posted on the financial companies of the sales office, service department, and/or warehouse instead of on the financial company of the PCS project. If internal invoices are sent from the PCS project to those departments, and the internal invoices are not completed yet, the Close Project (tipcs2250m000) session sets the project status to To be Closed instead of to Closed. You must first complete the internal invoices, and then run the Close Project (tipcs2250m000) session again to set the project status to Closed.

Archived
The project has been archived. This means that all project data has been stored in archive files and is removed from the original files.

Previous Article Infor LN & Baan Tip: LN Order Management - Generating Purchase Receipts
Next Article Infor LN & Baan Tip: Cost Component Setup
Print
56200 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories