Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 105091 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 83401 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 111472 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 82706 Article rating: No rating
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

BPCS/LX Tip of the Week: The Item Master Requirements Code

Anthony Etzel 0 78095 Article rating: No rating

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

Grindmaster Cecilware Selects Crossroads RMC For Baan IV / Davisware Integration

Crossroads RMC 0 41434 Article rating: No rating

Grindmaster Cecilware, a leader in the development of products for the food and beverage industry, has selected Crossroads RMC to integrate their Baan IV system to Davisware Global Warranty. Davisware is an electronic customizable online solution that fits almost any warranty process. Grindmaster’s customers will be able to access the Davisware software online and process warranty claims which will then automatically feed back into the Baan IV system for further review and processing. The integration is expected to go live in Q1 of 2015.

First122123124125127129130131Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Finance Tip: What Can You Do in the Financial Statements Module?

In the Financial Statements module, you can:

  • Define financial statements, and link a structure of child statement accounts and parent statement accounts to these financial statements.
  • Link ledger accounts and/or dimensions to the statement accounts.
  • Link cash flow reasons to cash flow statement accounts.
  • Export financial data to FST reporting tables.
  • Print reports directly, or use the BIRT report functionality to print to PDF, HTML, and export to Excel or Word.

Data drill down in financial statements - You can use various Financial Statements sessions to view transactions in a hierarchical structure. You can also zoom back to the original logistic transaction.

Currency calculation - In Financial Statements, you can define a statement currency that is not one of the home currencies.

Financial statements in multi-tenant cloud -The Financials Statements module can now be used in the multi-tenant cloud. When generating the layouts, the reports are created in the Extensibility (tx) package.

Previous Article Infor LN & Baan Manufacturing Tip: All About Routings
Next Article Infor LN & Baan Materials Tip: Sales Quotations
Print
68629 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories