Baan/LN Tip of the Week: Back Dating Cycling Counting Orders

Kathy Barthelt 0 104808 Article rating: No rating

Cycle Count Orders cannot be directly “back dated” in Baan IV, Baan V or LN, however, there are some work-arounds.

In Baan IV you can do an inventory adjustment and back date. Just set all dates on the adjustment to the date you want and Baan will post the adjustment in that period.

In LN you can do a Cycle Count/ Adjustment and again back date and Baan will post to that period.

 

Unfortunately, there is no work-around for Baan V.

BPCS/LX Tip of the Day: Inventory Management

Anthony Etzel 0 74784 Article rating: No rating

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 

Baan/LN Tip of the Day: Chart of Accounts

Kathy Barthelt 0 108086 Article rating: No rating

Zero sublevel accounts are posting level accounts. All others are parent accounts. Once the balances have been updated in the child ledger accounts, the parents are automatically updated.

Inquiries and reports can be printed or displayed either by child accounts or by parent accounts. On line drill-down is possible from either child or parent.

BPCS/LX Tip of the Day: Cycle Counting Part 2

Anthony Etzel 0 75865 Article rating: No rating

Understanding: The Cycle Count Alternative

The best way to cycle count is to count the same number of items each day and at the same time each day. The goal is to count your “A” items 4 times a year. The “A” items should be those item that are about 80% of the total inventory value and 20% of the total items. Consider creating your own cycle count schedule then instead of using the cycle count transaction, use the inventory adjustment transaction. The item balance is changed at the time the transaction is keyed. The transaction list can be used for the reconciliation process.

Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 104578 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 82849 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 110886 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 82071 Article rating: No rating
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.
First120121122123125127128129Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: Pegging Material Supply Lines for Operation and Product Subcontracting

For project pegged production orders, operations can be subcontracted. The material delivered to the subcontractor can be project pegged or anonymous. The subassemblies sent and retrieved are always project pegged. Costing breaks can be applied to direct the costs of the subcontracted operation to a specific project cost account. If (production material) costing breaks are used, a purchase order line's peg can differ from the peg on the material supply line.

For product subcontracting, the subcontracted purchase orders can include materials that inherit the project pegs or can include anonymous materials. The pegged materials are stored in inventory and are shipped to the subcontractor with project pegged orders.

In case of a project pegged order, a peg distribution is linked to the Purchase Order Material Supply Line in the Purchase Peg Distribution (tdpur5100m000) session. For a specific purchase order line (detail) and material sequence, the material supply line's Order and Consumption quantities are distributed across the peg distribution lines for combinations of project/budget, project element, and/or project activity. The peg information in the Purchase Peg Distribution (tdpur5100m000) session includes the line number for the peg in the distribution, the peg (project, element, activity), and the material supply line quantity by peg. The peg distribution cannot be manually created and must always be generated using the parent.

For operation subcontracting, the purchase order line, the material supply line, and the linked peg distributions are generated by Job Shop Control and can only be updated by Job Shop Control.

For product subcontracting, the purchase order line, the material supply line, and the peg distributions are generated by Procurement. A material supply line's peg distribution can be updated only from the parent, that is the purchase order line, the purchase order line peg distribution, or the material supply line. If a purchase order line's distribution line is changed, and no quantities are received or consumed yet, the pegged fields on the linked material supply lines are synchronized to the updated distribution line in the Purchase Order Material Supply Lines (tdpur4116m000) session. However, if a different quantity distribution is applicable, the quantities of the material supply lines' distribution lines are redetermined in the Purchase Peg Distribution (tdpur5100m000) session.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Currency Differences
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Load Audit Tables for Profile (ttaud3220s000)
Print
467 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories