BPCS/LX Tip of the Day: Material Requirement Dates and Lead Time Offsets in MRP

Anthony Etzel 0 343 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Database Sizing – Moving to LN

Kathy Barthelt 0 219 Article rating: No rating
The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

How Do You Measure Success in Your Business?

Anthony Etzel 0 52950 Article rating: 5.0

Business owners may measure success in different ways – some tangible, some intangible.

In order to establish how you should measure success for your business, you need to first examine how you measure your personal success. If you are a business owner, or a part of the management team of the company you work for, ask yourself these questions to see how you measure up:

Assess personal success.

1.    Am I happy in my job?

2.    Do I have passion for what I’m doing?

3.    Do I get the desired results based on the effort I’m putting in?

4.    Am I putting forth my best effort?

5.    Am I patient and allow for sufficient time to see results?

6.    Do I get respect from my co-workers?

7.    Do I have the endurance to hang in there when things get a bit rough?


Reflect on successes and failures.

After answering these questions, do you need to make any changes? Do you still have the same ambition and drive to achieve the goal? Are you content with your work, or have you come to the conclusion that you have not done your best?

To be successful...

Baan/LN Tip of the Week: Switching to a Difference Series

Kathy Barthelt 0 204 Article rating: No rating

In general, you can enter a different series in the order field if you have an available series.

To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1). Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

BPCS/LX Tip of the Day: MRP/MPS Simulation

Anthony Etzel 0 786 Article rating: No rating
The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

BPCS/LX Tip of the Day: Inventory Stocking Levels – LX

Anthony Etzel 0 735 Article rating: No rating

The system supports four levels of inventory. You can view summaries of stock at each level through the Material Status Inquiry program or through reports.

 

Below are the four levels:

â–ª  Item

â–ª  Item + warehouse

â–ª  Item + warehouse + location

â–ª  Item + warehouse + location + lot

 

The lot number level and/or container of inventory can cross multiple warehouses and locations. For example, item + lot or item + lot + container. Locations exist within warehouses. There is no limit on the number of warehouses, locations, or lots that you can assign to an item.

Baan/LN Tip of the Day: Transfers - LN

Kathy Barthelt 0 2779 Article rating: No rating
A Transfer involves either one or two warehouses. If items are transferred between two different warehouses, all activities of the warehousing procedures must be carried out. However, if a transfer takes place between two locations within the same warehouse, the receipt activities are not carried out. You can use transfer orders to define a replenishment system within a single warehouse. This system controls replenishment from bulk locations to pick locations. Note: LN allows you to modify the outbound order line data based on the value the Allow Updating Outbound Order Lines up to and including field is set to in the Warehousing Order Types (whinh0110m000) session.

BPCS/LX Tip of the Day: LX Inventory Pallet Status Flow

Anthony Etzel 0 49971 Article rating: No rating

Four fields in the Item/Warehouse record (IIW file) affect the disposition of the

pallet status.

 

1.  Goods Receiving Code: You define these codes in Goods Receiving Maintenance (WHM130). The codes control whether or not the stock passes through inspection, what percentage, or quantity of a delivery to inspect, and the number of quarantine days, if any.

 

2.  Inspection Zone/Inspection Location: Either the Inspection Zone or the Inspection Location must be entered on the Item/Warehouse Master Maintenance screen WHM150D2-01.

 

First112113114115117119120121Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Crossroads RMC

Unlocking Success: The Power of Staff Augmentation with Crossroads RMC

Infor LX, BPCS, Infor M3, Infor LN & Baan

Consider this...

Your team is currently engaged in a critical project for your top client. However, to ensure the project's timely completion and high customer satisfaction, it's imperative to expand your team. You're aware that the recruitment process is time-consuming, and finding highly qualified individuals who don't require extensive training, especially in your ERP system and your specific business, is a challenging task.

Or perhaps this situation sounds familiar...

Your ERP system is running sluggishly, and you're aware that there are updates available that could enhance system performance. Unfortunately, your IT specialist is currently occupied with other tasks, and there's uncertainty about when the upgrade can be executed.

Both of these scenarios reflect the challenges businesses face in our era of rapid technological advancement. To maintain competitiveness, it's essential to meet client demands and ensure the smooth operation of internal systems, preventing any hindrances to current production. The hard reality is that your success hinges on having expert staff who can make an immediate, positive impact on your business.

So, how can you consistently maintain the right team size and composition to address contemporary challenges when hiring new personnel is a costly, protracted process?

The solution is staff augmentation. Whether you need to tackle immediate challenges or plan for the future, Crossroads RMC has got you covered. Our team is equipped to deliver top-tier ERP consulting and round-the-clock support services, ensuring your systems operate smoothly and your staff remains at peak productivity.

The Crossroads team offers on-demand resources in various areas, including:

  • Manufacturing Planning
  • Warehousing
  • Finance
  • Distribution
  • Customization
  • Integration
  • Data Migration
  • Upgrades & Implementations
  • ION / Infor OS Consulting
  • Report Development

And much more!

Reach out to Crossroads RMC today to explore how our team can assist your team in overcoming your most significant business challenges.

Contact Crossroads RMC today to discuss how our team can help your team solve your biggest business challenges. 800-762-2077

Learn more about our support services for:
Infor LN>
Baan>
Infor LX>
BPCS>

Print
13435 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories