Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 1943 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Day: Cost Accounting – LX

Anthony Etzel 0 868 Article rating: No rating

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

â–ª Four sets of costs: actual, standard, frozen standard, and simulated

â–ª Nine user-defined elements per set

â–ª Full and partial cost roll-up and simulation

â–ª Cumulative in-process cost tracking

â–ª Cost summaries by item

â–ª Cost definition tied to work centers or material type

â–ª Process hour costing

Baan/LN Tip of the Day: Vendor Rating

Kathy Barthelt 0 1416 Article rating: No rating

In LN, a supplier's reliability is no longer based only on correct deliveries. The vendor rating functionality of LN is based on various objective criteria and subjective criteria that can be used to calculate the vendor’s rating.

 

The set up procedure for analyzing suppliers has changed completely compared to Baan IV.  To execute the vendor rating process, users must update the vendor ratings in the Update Vendor Rating (tdpur8850m000) session.

If users update the vendor ratings, the following stages exist in the update vendor rating procedure:


1. Calculate actual weightings

2. Calculate ratings for objective criteria

3. Calculate ratings for subjective criteria

4. Update overall vendor rating

Baan/LN Tip of the Day: Release Commissions/Rebates to Invoicing

Kathy Barthelt 0 3103 Article rating: No rating

In Baan IV, this session is called Release Commissions/Rebates to Invoicing (tdcms2201m000) and is used to set the status of the commissions/rebates to Reserved, or Closed. In Infor LN, this session is only used to set the status to  Closed. Users can reserve commissions/rebates in the Reservation and Approval of Reserved Commissions/Rebates (tdcms2202m000) session. In addition, the following fields are added to the Release Commissions/Rebates to Invoicing (tdcms2201m000) session:

â–ª Commissions to Accounts Payable

â–ª Rebates to Central Invoicing

BPCS/LX Tip of the Day: How Does LX Fit in With Just-In-Time?

Anthony Etzel 0 364 Article rating: No rating

For years, repetitive manufacturing industries have been applying many of the principles in Just-in-Time philosophy. They have established balanced production lines that depend on a steady flow of material to each work station. They schedule production in daily or weekly rates rather than in discrete shop order lots. They track finished inventory by work center rather than by job. They typically backflush stock balances (decrement stock balances upon completion of specific manufacturing steps rather than issued at the beginning of each production run).

 

Costing is typically based upon a daily rate or hourly rate rather than being associated with specific shop orders. 

 

Repetitive manufacturers use MRP II software adaptable to their environments

in the following key areas:


â–ª Product definition

â–ª Inventory tracking

â–ª MRP/Master Scheduling

â–ª Shop Floor Control

â–ª Purchasing

â–ª Costing

BPCS/LX Tip of the Day: What is Just-In-Time?

Anthony Etzel 0 313 Article rating: No rating

Just-in-Time (JIT) is a management philosophy that focuses on minimizing the resources necessary to add value to your products and to operate your factory in ways that eliminate waste. Resources are labor, materials, equipment, space, and time. Waste is anything that does not add value to your products. Moving work-in-process from place to place, stacking and sorting, investing capital in large work-in-process and raw material inventories, inspecting materials at your vendors' sites, and tying up warehouse space with finished goods are all activities that add cost, not value, to your products. 

JIT is a process that reduces lead time. JIT does not replace an MRP, an inventory program, a scheduling technique to bypass your Master Schedule, or a materials management project. JIT is the never-ending commitment of everyone, from top management to your workers on the floor, to maximize your effectiveness through continuous, incremental improvements.

Baan/LN Tip of the Day: Configuring Items

Kathy Barthelt 0 2237 Article rating: No rating

In LN, the configuration of a generic item not always results into a customized item. Configured items can now be customized items as well as standard items. If users configure items without PCS projects, standard items are generated instead of customized items.

 

The sessions for generating product variant structures for sales quotations and sales orders are moved from the Product Configuration module in Manufacturing to the Sales Control module in LN. The following new sessions are available in Sales Control:

â–ª Generate (Budget) Structure for Sales Quotations (tdsls1201m100).

â–ª Generate (Project) Structure for Sales Orders (tdsls4244m000)

BPCS/LX Tip of the Day: Shop Order Control

Anthony Etzel 0 443 Article rating: No rating

To create and maintain shop orders use SFC500 Shop Order Entry Maintenance. These orders use the standard bill of material (BOM) as the base list of components. You can also set up standard routings, which list the operations,

or work steps, involved in manufacturing.

 

To release shop orders, use the Shop Order Release program, SFC505. Infor ERP LX groups shop orders by user ID for batch processing. Use Shop Packet Print, SFC520, to print the shop orders that you select. SFC530 allows you to create multi-level shop orders to link shop orders together with a common end item parent. Linking multiple shop orders together for a final assembly product provides support for make-to-order and engineer-to-order manufacturing environments which need to schedule these multiple orders together or as a vertical slice in the production schedule.

 

You can make changes to shop orders after you print them. Use Shop Order Entry/Maintenance, SFC500, to update the shop orders. Changes are immediately visible on the inquiry screens for SFC300 and SFC350. To reprint the shop packet, use Reprint Shop Packet, SFC560.

First110111112113115117118119Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Crossroads RMC

Unlocking Success: The Power of Staff Augmentation with Crossroads RMC

Infor LX, BPCS, Infor M3, Infor LN & Baan

Consider this...

Your team is currently engaged in a critical project for your top client. However, to ensure the project's timely completion and high customer satisfaction, it's imperative to expand your team. You're aware that the recruitment process is time-consuming, and finding highly qualified individuals who don't require extensive training, especially in your ERP system and your specific business, is a challenging task.

Or perhaps this situation sounds familiar...

Your ERP system is running sluggishly, and you're aware that there are updates available that could enhance system performance. Unfortunately, your IT specialist is currently occupied with other tasks, and there's uncertainty about when the upgrade can be executed.

Both of these scenarios reflect the challenges businesses face in our era of rapid technological advancement. To maintain competitiveness, it's essential to meet client demands and ensure the smooth operation of internal systems, preventing any hindrances to current production. The hard reality is that your success hinges on having expert staff who can make an immediate, positive impact on your business.

So, how can you consistently maintain the right team size and composition to address contemporary challenges when hiring new personnel is a costly, protracted process?

The solution is staff augmentation. Whether you need to tackle immediate challenges or plan for the future, Crossroads RMC has got you covered. Our team is equipped to deliver top-tier ERP consulting and round-the-clock support services, ensuring your systems operate smoothly and your staff remains at peak productivity.

The Crossroads team offers on-demand resources in various areas, including:

  • Manufacturing Planning
  • Warehousing
  • Finance
  • Distribution
  • Customization
  • Integration
  • Data Migration
  • Upgrades & Implementations
  • ION / Infor OS Consulting
  • Report Development

And much more!

Reach out to Crossroads RMC today to explore how our team can assist your team in overcoming your most significant business challenges.

Contact Crossroads RMC today to discuss how our team can help your team solve your biggest business challenges. 800-762-2077

Learn more about our support services for:
Infor LN>
Baan>
Infor LX>
BPCS>

Print
13435 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories