Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 83969 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 58212 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 59469 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 28762 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 63182 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 57333 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 60772 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items

Kathy Barthelt 0 66945 Article rating: 3.0

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

First107108109110112114115116Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Crossroads RMC

Unlocking Success: The Power of Staff Augmentation with Crossroads RMC

Infor LX, BPCS, Infor M3, Infor LN & Baan

Consider this...

Your team is currently engaged in a critical project for your top client. However, to ensure the project's timely completion and high customer satisfaction, it's imperative to expand your team. You're aware that the recruitment process is time-consuming, and finding highly qualified individuals who don't require extensive training, especially in your ERP system and your specific business, is a challenging task.

Or perhaps this situation sounds familiar...

Your ERP system is running sluggishly, and you're aware that there are updates available that could enhance system performance. Unfortunately, your IT specialist is currently occupied with other tasks, and there's uncertainty about when the upgrade can be executed.

Both of these scenarios reflect the challenges businesses face in our era of rapid technological advancement. To maintain competitiveness, it's essential to meet client demands and ensure the smooth operation of internal systems, preventing any hindrances to current production. The hard reality is that your success hinges on having expert staff who can make an immediate, positive impact on your business.

So, how can you consistently maintain the right team size and composition to address contemporary challenges when hiring new personnel is a costly, protracted process?

The solution is staff augmentation. Whether you need to tackle immediate challenges or plan for the future, Crossroads RMC has got you covered. Our team is equipped to deliver top-tier ERP consulting and round-the-clock support services, ensuring your systems operate smoothly and your staff remains at peak productivity.

The Crossroads team offers on-demand resources in various areas, including:

  • Manufacturing Planning
  • Warehousing
  • Finance
  • Distribution
  • Customization
  • Integration
  • Data Migration
  • Upgrades & Implementations
  • ION / Infor OS Consulting
  • Report Development

And much more!

Reach out to Crossroads RMC today to explore how our team can assist your team in overcoming your most significant business challenges.

Contact Crossroads RMC today to discuss how our team can help your team solve your biggest business challenges. 800-762-2077

Learn more about our support services for:
Infor LN>
Baan>
Infor LX>
BPCS>

Print
13450 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories