BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 66611 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 85082 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 58794 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 60599 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 29028 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 63876 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 57921 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 61371 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

First111112113114116118119120Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Harnessing the Power of AI to Help Manufacturers Sell More at the Right Time

AI: Transforming Manufacturing—From Production to Profitability

As AI reshapes industries, manufacturers ask critical questions: How will customers discover and purchase products in an AI-driven world? And how can companies keep pace with these advancements?

At Crossroads RMC, we address these challenges with our AI Readiness Assessment (AIRA). An AIRA creates a clear, actionable digital roadmap, significantly boosting efficiency, accuracy, and strategic capabilities. This assessment ensures a smooth, swift AI transition.

AI Readiness Assessment targets key Financial areas:

  • Cash Flow Management: AI improves cash flow forecasting, identifying potential shortfalls before they impact operations.

  • Cost Control: By analyzing spending patterns, AI reveals areas for cost reduction; maintaining quality and efficiency.

  • Financial Forecasting: AI uses historical data and market trends to enhance forecasting accuracy, empowering strategic financial decisions.

AI Readiness Assessment targets key Operations areas:

  • Production Planning: AI optimizes production planning by analyzing data and forecasting demand, helping to balance workloads and minimize downtime.
  • Supply Chain Disruptions: AI predicts potential disruptions and suggests alternative suppliers or routes, enhancing supply chain resilience.
  • Quality Control: AI detects defects in real-time and predicts quality issues before they occur, leading to higher consistency and fewer recalls.


AI Readiness Assessment targets key Technology areas:

  • Data Management: AI organizes, analyzes, and develops actionable insights from data.
  • Security and Compliance: AI enhances cybersecurity measures by detecting anomalies and potential threats in real-time, and automates compliance checks to ensure adherence to regulatory standards.
  • Performance Monitoring: AI continuously monitors system performance and identifies areas for improvement, ensuring optimal operation.
     

AI Readiness Assessment target key Executive areas:

  • Operational Visibility: AI integrates data from various sources to provide real-time visibility into all aspects of the business, enhancing oversight and control.
  • Risk Management: AI analyzes market trends, supply chain data, and internal processes to identify potential risks and recommend mitigation strategies.
  • Market Competitiveness: AI provides insights into market trends, customer preferences, and competitor activities, helping executives stay ahead of the curve.

How the Crossroads/Aleran can help you modernize your business through the use of AI (27:36)

Watch our video to learn more!

Connect with us at 800.762.2077, solutions@crossroadsrmc.com, or request an AI Readiness Assessment to start your path towards a flexible, future-proof ERP.
 