BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 66470 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 84969 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 58632 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 60509 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 28926 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 63732 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 57830 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 61262 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

First111112113114116118119120Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

[EasyDNNnews:IfExists:Event]
[EasyDNNnews:IfExists:EventRegistration][EasyDNNnews:EventRegistration:RegisterButton][EasyDNNnews:EndIf:EventRegistration] [EasyDNNnews:IfExists:Payment][EasyDNNnews:Price][EasyDNNnews:EndIf:Payment] [EasyDNNnewsLocalizedText:Eventdate]: [EasyDNNnews:EventDate] [EasyDNNnewsLocalizedText:ExportEvent] [EasyDNNnews:IfExists:EventLocation]

[EasyDNNnewsLocalizedText:EventLocation]: [EasyDNNnews:EventLocation]

[EasyDNNnews:EndIf:EventLocation] [EasyDNNnews:IfExists:EventRegistration]
  • [EasyDNNnewsLocalizedText:NumberOfAttendants]: [EasyDNNnews:EventRegistration:NumberOfAttendants]
  • [EasyDNNnewsLocalizedText:MaxNumberOfTickets]: [EasyDNNnews:EventRegistration:MaxNumberOfTickets]
  • [EasyDNNnewsLocalizedText:NotUsedTickets]: [EasyDNNnews:EventRegistration:NotUsedTickets]
  • [EasyDNNnews:IfExists:Payment]
  • [EasyDNNnewsLocalizedText:Price]: [EasyDNNnews:Price]
  • [EasyDNNnews:EndIf:Payment]
[EasyDNNnews:EventRegistration:InfoMessage] [EasyDNNnews:EndIf:EventRegistration] [EasyDNNnews:IfExists:EventSignUp]

[EasyDNNnewsLocalizedText:AreYouGoing]

[EasyDNNnews:SignUpActionBar]
[EasyDNNnews:EndIf:EventSignUp]
[EasyDNNnews:EndIf:Event]
George Moroses
/ [EasyDNNnewsLocalizedText:Categories]: [EasyDNNnews:Categories]

Infor LX & BPCS: Why You Need MES

You know your plant better than anyone, and most likely you'd admit that there is room for improvement. Perhaps too many defects are causing costly issues down the road, or maybe your production is behind and orders are shipping late? Do you know what needs to be improved? Do you know about the root causes of the problems that you’re experiencing? Is it fair to say, you don’t know what you don’t know … yet?

MES helps you dig into the problem and better yet, SOLVES the problem!

What Is MES and How Does It Work?

Many companies still enter data manually or share work instructions on paper. Most of them, however, know there’s a better way to organize the mass of activity happening on the plant floor. MES provides visibility to that activity as well as the underlying data and uses that data to improve how that activity is done and makes it repeatable. MES connects multiple sites, integrates with equipment, and raises the effectiveness of business applications all to better optimize operations.

The 3 Pillars of MES:

  1. Establishing a plan and staying on schedule. The system takes your input — production shifts/times, production goals, etc. — and calculates the rate at which you need to complete production in order to meet customer demand. Operators see real-time progress on dashboard graphics, knowing the progress at every moment.
  2. Enforcing a repeatable process. Knowing your process is being followed exactly as defined provides the ultimate peace of mind. Every target, from fastening to product routing, is achieved just as you defined it time after time.
  3. Creating a rich data set. Capturing data is one thing; being able to act on that data is really the key to driving improvement initiatives. Use your analytics, explore your data set, and identify and solve your hidden inefficiencies.

All three of these MES pillars are used to help you reach productivity and quality goals by:

  • Solving production scheduling challenges
  • Discovering and sharing your best operators’ insights
  • Uncovering inefficiencies in your process and fixing them
  • Reducing the exhausting task of putting out fires
  • Establishing a continuous improvement philosophy
  • Increasing operator engagement and dedication

And if you need another reason... according to Forbes.com, MES ranks in the Top 5 Key Areas to Affect How Goods Are Made in 2023 - Five Predictions For Manufacturing And Logistics In 2023.
https://www.forbes.com/sites/forbestechcouncil/2023/02/13/five-predictions-for-manufacturing-and-logistics-in-2023/?sh=1155863f1f76

So, what's next? Work with Crossroads RMC, an experienced MES partner who has seen situations just like yours and who has guided companies in your position. And best of all, Crossroads RMC doesn’t just know MES, we have a team of experts who are knowledgeable about manufacturing best practices, your Infor ERP, and MES and can bring all of that knowledge together to help you formulate the right plan for your company’s success.

Contact Anthony Etzel at Crossroads RMC today. He can provide you with a free MES ROI calculator to give you some concrete numbers to help you see what MES can do for your business. 800.762.2077