Baan/LN Tip of the Week: Setting Up New Employees in LN

Kathy Barthelt 0 53422 Article rating: No rating

In LN, the People package is used to register the employee’s hours and expenses. To support the People package, the Employees - General (tccom0101m000) session only contains the general employee data.

The title of the Employees - General (tccom0101m000) session was changed to Employees – General (tccom0101m000).

From the Employees - General (tccom0101m000) session, users can start the following sessions to define the more specific employee data:

  • Employees - People (bpmdm0101m000).
  • Employees - Project (tppdm8101m000).
  • Employees - Service (tsmdm1140m000).
  • Skills by Employee (tcppl0120m000).
  • Employees by Team (tcppl0150m000).
  • Roles by Employee (tcppl0170m000).

After users define the employees, users can also start the listed sessions from the Employees Dashboard (bpmdm0101m100) session in People.

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Anthony Etzel 0 44665 Article rating: No rating

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

BPCS/LX Tip of the Week: Changing the Master Schedule

Anthony Etzel 0 760 Article rating: No rating

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 1086 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 1064 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 1101 Article rating: No rating

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Why define location fields in the work center file?

Anthony Etzel 0 568 Article rating: No rating

If you setup the “From” and “To” Location fields in the Work Center file, this will then determine the locations for material issue transactions and production reporting transactions.

The reporting of the transactions would happen through production reporting, JIT600, or using the Shop Floor labor posting, SFC600, or Shop Floor Posting from SFC650.

Remember, any location used in the work center file must first be set up in the location master file. Using an MES solution by-passes the need to key any of the data to ERP LX.

First107108109110112114115116Last

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: Important Porting Set Announcement (all versions of LN & Baan)

There has been a recent porting set change due to Infor’s Product Life Cycle Policy.  

How to determine the maintenance stage of an Infor LN product version and release

Before a customer starts deploying Porting Set 9.4a or a later release, they must determine the actual maintenance stage of their Baan / Infor LN product. The definition of the maintenance stages for the product versions and releases of all versions of Baan and Infor LN are outlined in the Product Support schedule as published in the PLC policy. The maintenance stage of the ERP version is either “Mainstream Maintenance”, “Extended Maintenance” or “Sustaining Maintenance”.

How to manage Porting Set updates

The following conditions apply to customers who intend to upgrade to Porting Set 9.4a or later Porting Set releases:

  • For customers with a product version in Mainstream Maintenance, there will be no difference with regards to Porting Set updates. They can install Porting Set 9.4a or any newer release.
  • Customers with a product version in Extended Maintenance will be able to use Porting Set 9.4a only under the condition that they acquire an Extended Maintenance license and have applied the corresponding validated license key to their SLM License server. This key is a Server license type.
  • Customers with a product version in Extended Maintenance who have not acquired an Extended Maintenance license will not be able to use Porting Set 9.4a or any newer version. The latest Porting Set for these customers that can be installed and used is 9.3j which was released in April 2021.
  • Customers with a product version in Sustaining Maintenance will not be able to use Porting Set 9.4a or any newer version. The latest Porting Set for these customers is 9.3j which was released in April 2021. Customers who are not entitled to upgrade to Porting Set 9.4a can use any Porting Set release prior to Porting Set 9.4a. These continue to be available through the Infor Support Portal.

You can find more information in KB 1946498 General: Infor LN and Baan Product Lifecycle Policy and KB 2204515, or you may contact Crossroads RMC for assistance in determining whether or not you are able to upgrade your porting set.

800.762.2077

Previous Article Don't laugh - the average lifespan of an ERP system is 7-10 years
Next Article Infor LN & Baan Tip: Save Space in General Ledger
Print
55057 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories