Baan/LN Tip of the Week:GRINYA Reconciliation – What Could Go Wrong?

Kathy Barthelt 0 77724 Article rating: No rating

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan or LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error.

To ensure, it’s recommended that the Integrations Setup tables should be audited either through Baan/LN or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Morrison Brothers Goes Live With Crossroads MES in Record Time!

Crossroads RMC 0 31929 Article rating: No rating

On February 18, 2016, the Maquoketa plant of Morrison Brothers went live with the Crossroads MES solution. The goal was to remove all the shop floor paperwork and eliminate the manual recording of production and labor. The company achieved this goal in just 96 days from project kick-off to go live. Included in the go-live was the ability to deliver drawings electronically to the Crossroads MES workstations. This was a critical component of the implementation as it ensured that each workstation would always be operating off the latest revision of the engineering documents.

A rollout of the Crossroads MES solution is planned for Morrison’s Dubuque plants later this year. 

Morrison Brothers is a major producer of petroleum marketing equipment in the United States and abroad.

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 73258 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 51330 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 84814 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i

Kathy Barthelt 0 32828 Article rating: No rating

Crossroads RMC is proud to announce the official release of NextTrack Sales – a sales analysis tool for Baan, LN, and IBM i. NextTrack Sales allows you to get the “big picture”, or get down into the finer details. The tool provides a sophisticated pivot grid and charting functionality, export to Excel, PDF printing, and emailing capabilities to bring your sales data to life. Analyze your Baan Sales data to examine trends, identify market opportunities, and much more. Click here for more details.

Mount Olive Pickle Chooses Crossroads RMC for BPCS Data Collection

Anthony Etzel 0 29175 Article rating: 5.0

Mount Olive Pickle, a leading producer of pickles, peppers, and relishes in the United States, has chosen Crossroads RMC as their solutions vendor for data collection and manufacturing production reporting. In the first phase of the project, the Crossroads team will implement the Inventory Visibility Data Collection software connected to BPCS. The transactions to be implemented include PO Receipts, Transfers, Component Issues, Cycle Counting, and Production Receipts.  

First106107108109111113114115Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: Pegging Material Supply Lines for Operation and Product Subcontracting

For project pegged production orders, operations can be subcontracted. The material delivered to the subcontractor can be project pegged or anonymous. The subassemblies sent and retrieved are always project pegged. Costing breaks can be applied to direct the costs of the subcontracted operation to a specific project cost account. If (production material) costing breaks are used, a purchase order line's peg can differ from the peg on the material supply line.

For product subcontracting, the subcontracted purchase orders can include materials that inherit the project pegs or can include anonymous materials. The pegged materials are stored in inventory and are shipped to the subcontractor with project pegged orders.

In case of a project pegged order, a peg distribution is linked to the Purchase Order Material Supply Line in the Purchase Peg Distribution (tdpur5100m000) session. For a specific purchase order line (detail) and material sequence, the material supply line's Order and Consumption quantities are distributed across the peg distribution lines for combinations of project/budget, project element, and/or project activity. The peg information in the Purchase Peg Distribution (tdpur5100m000) session includes the line number for the peg in the distribution, the peg (project, element, activity), and the material supply line quantity by peg. The peg distribution cannot be manually created and must always be generated using the parent.

For operation subcontracting, the purchase order line, the material supply line, and the linked peg distributions are generated by Job Shop Control and can only be updated by Job Shop Control.

For product subcontracting, the purchase order line, the material supply line, and the peg distributions are generated by Procurement. A material supply line's peg distribution can be updated only from the parent, that is the purchase order line, the purchase order line peg distribution, or the material supply line. If a purchase order line's distribution line is changed, and no quantities are received or consumed yet, the pegged fields on the linked material supply lines are synchronized to the updated distribution line in the Purchase Order Material Supply Lines (tdpur4116m000) session. However, if a different quantity distribution is applicable, the quantities of the material supply lines' distribution lines are redetermined in the Purchase Peg Distribution (tdpur5100m000) session.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Currency Differences
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Load Audit Tables for Profile (ttaud3220s000)
Print
503 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories