BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 1

Anthony Etzel 0 54811 Article rating: 5.0

Understanding: How many hours remain in total and at each operation?

First let’s look at some key BPCS Master File data starting with the routing file.

How many routing steps (operations) are set up that reflect how the product is produced in the factory? If you take a short cut and set up only one operation for the entire process, then you will limit the information seen on the SO inquiry program. Set up the operation steps to reflect what you want to report back to from the factory floor.

Will each of the routing steps run in one work center, or in different work centers? To keep it simple you may want to set up work centers as departments. For example:

  • Assembly
  • Machine
  • Paint
  • Etc.

For each operation setup consider how you have set up the following:

  • Load Codes – for example a code 5 is used if reporting both setup time and run labor time. These codes are maintained in the work center file
  • Basis Code – typical codes are P for pieces per hour,  3 is used for hours per 1,000 pieces
  • Setup hours – if you set them up, you also want to report them
  • Run hours – Direct Labor
  • Machine hours

How you set up th

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 56329 Article rating: No rating

You may have started your setup of your ERP system one way, and have discovered over time that maybe it no longer fits how you need to do business. Over the next few weeks, I’ll be providing some pros/cons to consider for different company setups.

Pros/Cons of Single Finance / Single Logistic Company Set-Up

Pros
Easy to implement and to maintain.
No risk of processing data for another company.
Data not visible across companies – pro if you do not want users to see other company’s data.
Cost Prices can be different for the same item in the different logistics companies.
Easy to add or remove companies when companies are bought or sold.
Accounting functions are all separate by company. – Pro if each finance company is managed separately.
 

 

Cons
Decentralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
User must go in and out of companies if there is a need to view or create transactions in more than one company.

It’s NOT All About the Money, Money, Money… Motivating Employees in the New Year!

Kathy Barthelt 0 37439 Article rating: 5.0

Have you ever thought about what really motivates your employees?

It’s not about the almighty dollar, you know. Ok, ok…..money doesn’t hurt, but money alone doesn’t keep most people in their jobs. You actually need to motivate your employees to keep them showing up, mentally, and physically. Employees that don’t feel motivated are probably underperforming, and that means you’re losing money.

Ask yourself these questions about your employees:

  • Are they happy…..YES….HAPPY! Do they enjoy coming to work every day?
  • Do they feel challenged, or do they feel demeaned?
  • Are they sinking, or are they swimming?
  • Do they have the right tools in their arsenal to battle the giants?
  • Where’s the reward?

Happiness - I’ve worked with manufacturers for almost 20 years now...

BPCS/LX Tip of the Week: Financial Year End – Have you done all you need to do?

Anthony Etzel 0 55952 Article rating: No rating

Came across an article online from Lauber CFO’s, and thought I would share. Here is a checklist for things to consider in order to finish out the year and help you plan for 2016:

 

  • Are your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to year end? 
  • Do you have a plan in place to properly “cut-off” revenue at year end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash f

Baan/LN Tip of the Week: Financial Year End – Have you done all you need to do?

Kathy Barthelt 0 50534 Article rating: No rating

Came across an article online from Lauber CFO’s, and thought I would share. Here is a checklist for things to consider in order to finish out the year and help you plan for 2016:

  • Is your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year-end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to the year-end? 
  • Do you have a plan in place to properly “cut-off” revenue at year-end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions, or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash flow?
  • Will you be in compliance with your bank covenants at year-end?
  • Do you need to make arrangements to receive statements as of the end of the year for the cash value of life insurance, loan balances, etc.?

BPCS/LX Tip of the Week: Using Pre-Assigned Lot Numbers

Anthony Etzel 0 50450 Article rating: No rating

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

CST Adds Warranty Service Claim System to Dealer Portal for LN

Crossroads RMC 0 31893 Article rating: No rating

Crossroads RMC has once again partnered with Xenitel Managed Service Solutions and CST Industries to create a warranty service claim system for CST’s dealers. The project will provide a way for dealers to create a “warranty request claim” from within the dealer portal, defining the customer and product, and parts that failed, and selecting what parts they are claiming for replacement to install the replacement part. This service will be offered in addition to the parts online ordering system previously developed for CST. 

 

CST is a global leader in the manufacture and construction of factory coated metal storage tanks, aluminum domes and specialty covers.

First103104105106108110111112Last

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: Latest Porting Set – All Versions of Infor LN & Baan

Are you on the latest porting set for your version of Baan / Infor LN? Check here to be sure:

VERSIONS: Infor LN, Infor Baan ERP 5.0c, Infor Baan IVc4

LAST MODIFIED ON:
13th Jan, 2021: Updated with 9.3i porting set, see KB 2176336 for this version. Available from LN CE release 2021.01
9th Oct, 2020: Updated with 9.3h porting set, see KB 2158949 for this version. Available from LN CE release 2020.10
9th July, 2020: Updated with 9.3g porting set, see KB 2142625 for this version. Available from LN CE release 2020.07
10th April, 2020: Updated with 9.3f porting set, see KB 2125567 for this version. Available from LN CE release 2020.04
13th Jan, 2020: Updated with 9.3e porting set, see KB 2108810 for this version
11th Oct, 2019: Updated with 9.3d porting set, see KB 2093165 for this version
11th July, 2019: Updated with 9.3c porting set, see KB 2075437 for this version
13th March, 2019: Updated with 9.3b porting set, see KB 2051365 for this version
7th Dec, 2018: Updated with 9.3a porting set, see KB 2033165 for this version
6th Sept, 2018: Updated with 9.2b.01 porting set, see KB 2014729 for this version
8th June, 2018: Updated with 9.2b porting set, see KB 1997100 for this version
12th March, 2018: Updated with 9.2a.01 porting set, see KB 1972861 for this version
11th Dec, 2017: Updated with 9.2a porting set, see KB 1954406 for this version
8th Sept, 2017: Updated with 9.1c.01 porting set, see KB 1934704 for this version
10th June, 2017: Updated with 9.1c porting set, see KB 1915968 for this version
20th March, 2017: Updated with 9.1b.01 porting set, see KB 1897691 for this version
9th Dec, 2016: Updated with 9.1b porting set, see KB 1876613 for this version
22nd Sept, 2016: Updated with 9.1a.01 porting set, see KB 1856545 for this version
23rd June, 2016: Updated with 9.1a porting set, see KB 1836486 for this version
14th March, 2016: Updated with 9.0c.01 porting set, see KB 1700568 for this version
11th Dec, 2015: Updated with 9.0c porting set, see KB 1677286 for this version
17th Sept, 2015: Updated with 9.0b.01 porting set, see KB 1654371 for this version
19th June, 2015: Updated with 9.0b porting set, see KB 1630218 for this version
20th March, 2015: Updated with 9.0a.01 porting set, see KB 1605781 for this version
9th Jan, 2015: Updated with 8.9a.06 porting set, see KB 1586121 for this version, this is only 32 bit for windows and linux.
17th Nov, 2014: Updated with 9.0a porting set, see KB 1572748 for this version, 12 Dec 2014, new version for windows released.
26th Sept, 2014: Updated with 8.9a.05 porting set, see KB 1539050 for this version
11th July, 2014: Updated with 8.9a.04 porting set, see KB 1517147 for this version
5th April, 2014: Updated with 8.9a.03 porting set, see KB 1490061 for this version
10th Jan, 2014: Updated with 8.9a.02 porting set, see KB 1465391 for this version
4th Oct, 2013: Updated with 8.9a.01 porting set, see KB 1442188 for this version
19th July, 2013: Updated with 8.9a porting set, see KB 1422389 for this version
1st March, 2013: Updated with 8.8a.03 porting set, see KB 1381629 for this version
30th Nov, 2012: Updated with 8.8a.02 porting set, see KB 1356958 for this version
13th Sept, 2012: Updated with 8.8a.01 porting set, see KB 1181506 for this version
30th May, 2012: Updated with 8.8a porting set, see KB 1154144 for this version
19th Jan, 2012: Updated with 8.7b.01 porting set, see solution 1120445 for this version. This is the first version that can also be used for Infor BaanIV c
7th Oct, 2011: Updated with 8.7a.03 porting set, see solution 1062346 for this version
17th June, 2011: Updated with 8.7a.02 porting set, see solution 1025539 for this version
31st March, 2011: Updated with 8.7a.01 porting set, see solution 1007520 for this version
17th Jan, 2011: Updated with new version of 8.7a porting set
3rd Dec, 2010: Updated with 8.7a porting set, see solution 22945526 for this version
8th Oct, 2010: Updated with 8.6a.03 porting set, see solution 22899106 for this version
17th June, 2010: Updated with 8.6a.02 porting set, see solution 22899105 for this version
1st April, 2010: Updated with 8.6a.01 porting set, see solution 22899104 for this version
11th February, 2010: Updated with the 64-bit 8.6a porting set, see solution 22899103 for this version
1st Dec, 2009: Updated with new 8.6a porting set, see solution 22899103 for this version
1st Oct, 2009: Updated with new 8.5a.03 porting set, see solution 22899102 for this version
18th June, 2009: Updated with new 8.5a.02 porting set, see solution 22899101 for this version
19th March, 2009: Updated with new 8.5a.01 porting set, see solution 22899100 for this version
4th Dec, 2008: Updated with new 8.5a porting set, see solution 22899099 for this version
23th Oct, 2008: Updated with new 8.4c.02 porting set, see solution 22899098 for this version
23th July, 2008: Updated with new 8.4c.01 porting set, see solution 22899097 for this version
2nd July, 2008: Updated with new 8.4c porting set, see solution 22899096 for this version
13th March, 2008: Updated with new 8.4b porting set, see solution 22899095 for this version
24th Jan, 2008: Updated with new 8.4a.02 porting set, see solution 22899094 for this version
21st Dec, 2007: Updated with new 8.4a.01 porting set for Windows, see solution 22899093 for this version
31st Aug, 2007: Updated with new 8.4a.01 porting set, see solution 22899093 for this version
25th June, 2007: Updated with new 8.4a porting set, see solution 22899115 for this version
4th Jan, 2007: Updated with new 8.3a.01 porting set, see solution 22899114 for this version
20th Oct, 2006: Updated with new 8.3a porting set, see solution 22899113 for this version
23th Aug, 2006: Updated with new 8.2b porting set for windows, see solution 22899112 for this version
16th June, 2006: Updated with Porting set 8.2b: see solution 22899112 for this version
28th April, 2006: Updated with Porting set 7.6b_01: see solution 22899111 for this version
9th March, new version of 7.6b Porting set released, see solution below,(22899110)
6th Dec, 2005: Updated with Porting set 7.6b: see solution 22899110 for this version
15th June, 2005: Updated with Porting set 7.6a.02: see solution 22899109 for this version
27th April, 2005: Updated with Porting set 7.6a.01: see solution 22899108 for this version
4th Dec, 2004: Updated with Porting set 7.6a: see solution 22899107 for this version


SITUATION DESCRIPTION:
A porting set is a set of binaries, which are operating system dependent. It is the layer between the operating system and the application software. Infor regularly releases a new porting set. A bugfix number recognizes every modification made in the porting set.

Previous Article Infor LN & Baan Materials Tips: Serialized and Lot Controlled Items
Next Article Infor LN & Baan Tip: Performance Standard Cost
Print
54357 Rate this article:
4.5
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories