BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Anthony Etzel 0 54891 Article rating: 5.0

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: How is Your Productivity?

Kathy Barthelt 0 79815 Article rating: No rating

Are your employees not as productive as you’d like them to be? Are jobs not getting completed on schedule? 

Without actual data, making decisions about how efficient your operation is will be difficult. Start tracking actual time to complete each operation. Compare different production lines running the same job. Is one line running more efficiently? If so, start looking at why. Track downtime, setup, etc. Once you start really analyzing each piece of the puzzle, you can begin to uncover areas that are ripe for improvement.

Optimize Your Manufacturing Today!

Tip of the Week: Create a Repeatable Process

Kathy Barthelt 0 98629 Article rating: No rating

If you’ve been successful doing something in the past, you want to keep doing it that way. Are your procedures documented? Do you have workflows defined? Would creating video tutorials be helpful, especially for new employees? Giving employees the tools to be successful helps to ensure the success of the business as a whole.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: 6 Powerful Steps to Win With Automation

Anthony Etzel 0 52100 Article rating: 5.0
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.     
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: 6 Powerful Steps to Win With Automation

Kathy Barthelt 0 81119 Article rating: No rating
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.    
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 75589 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.

In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
    1. Price
    2. Quantity
    3. Vendor rating
    4. Delivery dates
    5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: Using Pre-Assigned Lot Numbers

Anthony Etzel 0 41453 Article rating: 5.0

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

Optimize Your Manufacturing Today!

Blonder Tongue Goes Live with Crossroads MES

Anthony Etzel 0 25413 Article rating: 5.0
Blonder Tongue Labs recently went live with the Crossroads MES solution over their current BPCS 6.0.4 environment. They selected the Crossroads MES solution for its shop floor management and reporting capabilities. Blonder Tongue is a leader in the field of cable-television communications products. They are planning an upgrade to LX and will expand the usage of Crossroads MES in the LX environment.
First8081828385878889Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Tip of the Week: 10 Ways to Succeed at an OEE Project Where 90% Fail

  1. Collect the requirements. Learn from everyone with the intent of developing a phased approach to implementing on your shop floor with OEE being Phase 1. 
  2. Create your list. Capture all of required functions, taking into account what the “output” of the system will be. What does the plant manager need to see in real-time? What KPI’s does each line need displayed in real-time? What reports are required?
  3. Insist Upon Real-time. In the moment data for the right OEE is the right approach. If it’s possible, collect the data automatically. Remember that real-time feedback to line operators results in an automatic increase in OEE.
  4. Evaluate your lines. Focus where production counts can be monitored automatically. If the data is in your PLC’s, can you get it out? OPC communication is the right way to go here. If not, the approach is to install a new dedicated PLC with sensors installed on each line.
  5. Find Your Data Points. If automatic production monitoring is not applicable, what will be your collection points and how will you collect the data?
  6. Calculate the Load. Determine how to load the “job” you’re reporting on into the OEE system. This will typically be the order/operation or the product from the ERP.
  7. Recognize Great Data. Do not accept “manual collection of data” as a viable approach because it produces false results and is labor-intensive.
  8. Be Tough. Evaluate systems based on OEE specificity to start and expandability to future phase functions as determined by your requirements. Plan to justify the OEE purchase on its own merits.
  9. Go Easy. Make sure the system is easy to implement. Software installation and configuration should take no more than 2 weeks.
  10. Be Simple. Put together a detailed but simple project plan indicating who will do what, how long it will take, and how you will monitor progress.
Read Full Article

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees
Next Article Tip of the Week: Gain Efficiency & Save Money - Evaluate Your Production Lines
Print
108387 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories