  1. Collect the requirements. Learn from everyone with the intent of developing a phased approach to implementing on your shop floor with OEE being Phase 1. 
  2. Create your list. Capture all of required functions, taking into account what the “output” of the system will be. What does the plant manager need to see in real-time? What KPI’s does each line need displayed in real-time? What reports are required?
  3. Insist Upon Real-time. In the moment data for the right OEE is the right approach. If it’s possible, collect the data automatically. Remember that real-time feedback to line operators results in an automatic increase in OEE.
  4. Evaluate your lines. Focus where production counts can be monitored automatically. If the data is in your PLC’s, can you get it out? OPC communication is the right way to go here. If not, the approach is to install a new dedicated PLC with sensors installed on each line.

BPCS/LX Tip of the Week: 5 Ways to Motivate Your Employees

Anthony Etzel 0 50626 Article rating: 5.0

Here are 5 ways you can motivate your employees to give their best every day:

1. Train Your Employees

2. Give Your Employees the Right Tools

3. Automate Processes

4. Give Your Employees Real-Time Feedback

5. Provide Incentives to Do More

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees

Kathy Barthelt 0 80137 Article rating: No rating

Here are 5 ways you can motivate your employees to give their best every day:

1. Train Your Employees

2. Give Your Employees the Right Tools

3. Automate Processes

4. Give Your Employees Real-Time Feedback

5. Provide Incentives to Do More

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Anthony Etzel 0 54297 Article rating: 5.0

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: How is Your Productivity?

Kathy Barthelt 0 79142 Article rating: No rating

Are your employees not as productive as you’d like them to be? Are jobs not getting completed on schedule? 

Without actual data, making decisions about how efficient your operation is will be difficult. Start tracking actual time to complete each operation. Compare different production lines running the same job. Is one line running more efficiently? If so, start looking at why. Track downtime, setup, etc. Once you start really analyzing each piece of the puzzle, you can begin to uncover areas that are ripe for improvement.

Optimize Your Manufacturing Today!

Tip of the Week: Create a Repeatable Process

Kathy Barthelt 0 96726 Article rating: No rating

If you’ve been successful doing something in the past, you want to keep doing it that way. Are your procedures documented? Do you have workflows defined? Would creating video tutorials be helpful, especially for new employees? Giving employees the tools to be successful helps to ensure the success of the business as a whole.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: 6 Powerful Steps to Win With Automation

Anthony Etzel 0 51551 Article rating: 5.0
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.     
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: 6 Powerful Steps to Win With Automation

Kathy Barthelt 0 79985 Article rating: No rating
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.    
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

First7778798082848586Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: Blocking or Unblocking Warehouses

You can block a warehouse for inbound procedures, outbound procedures, or both. For example, you can block inbound and outbound procedures for a warehouse if the warehouse must be closed temporarily for inspection.

You can impose these types of blockings:

  • Full block: Full block on warehousing procedures.

  • Interactive block: Override blocking allowed except blocks on confirm shipment or confirm receipt.

If you impose a full block on inbound procedures, the receipt and inbound inspection procedures are not allowed for the warehouse.

If you impose a full block on outbound procedures, the outbound, outbound inspection, and shipment procedures are not allowed for the warehouse.

An interactive block on inbound procedures blocks the confirm receipt step. For the other inbound steps (for goods already received), a warning is displayed and you are prompted to cancel the procedure or to continue.

These are the other inbound steps:

  • Generate and release inbound advice
  • Print and confirm storage lists
  • Put away stock

If you perform the outbound steps of a warehouse transfer and an interactive inbound block is imposed on the receiving warehouse, you are warned that the receiving warehouse is blocked.

An interactive block on outbound procedures blocks the confirm shipment step. For the remaining outbound and shipment steps, a warning is displayed and the user is prompted to cancel the procedure or to continue. Assembly, internal inventory movements and inventory adjustments are also allowed.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Interest Invoices
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Archiving Concept
Print
15582 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories