Infor LX & BPCS Tip of the Week: MPS vs. MRP

George Moroses 0 65079 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor/ERP LX will calculate cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

You’ve got a handle on your inventory requirements, right? Are you confident you can handle a rush order, or ten rush orders?

Baan & LN Add-Ons

Kathy Barthelt 0 35934 Article rating: 5.0

RMCbuild gives you the ability to report a component’s gross requirement, shortage, on-hand inventory, on-order inventory, allocated inventory, inspected inventory, production or work orders due to replenish component inventory, buyer or planner, and/or item group… and more.

RMCbuild takes all the surprise and guess work out of inventory planning. Give your employees the tools they need to do their job effectively.

Avalara isn't only tax calculation and returns filing....

Baan & Infor LN

Kathy Barthelt 0 40676 Article rating: 5.0

Did you know that in addition to tax calculation and returns filing, Avalara can also help with:

  • Business license and tax registration
  • Streamlined Sales Tax qualification
  • Nexus analysis and compliance
  • Tax document management including exemption certificates
  • Audit preparation

Contact us today! We partner closely with Avalara to provide you with solutions on ALL version of Baan and Infor LN!
 

Infor LN & Baan: Is Your House All In Order?

Kathy Barthelt 0 32235 Article rating: 5.0

Have you successfully closed all of the fiscal, tax and reporting periods for 2019 and closed the year? Sometimes this task hangs out there looming because either people don’t know what needs to be done, or there is a fear there are going to be problems.

Let Crossroads RMC’s expert finance consulting team help you through this.

Move into 2020 with ease! Contact Kathy Barthelt today to put together a plan for your close.
800.762.2077

Want a way to convert IBM i ® spool files into full-color, professional forms that are output as PDF documents?

Anthony Etzel 0 32694 Article rating: 5.0

Want a way to convert IBM i ® spool files into full-color, professional forms that are output as PDF documents?

Crossroads RMC and TL Ashford can help you get there!

TLAForms provide a reliable, feature-rich, cost-effective forms solution for IBM i, with no programming required!

Contact Anthony Etzel for more info: 1.630.955.1310, x125 or aetzel@crossroadsrmc.com

Join us in St. Louis for inPOWER 2020!

inPower 2020

George Moroses 0 31928 Article rating: 5.0

We can’t wait to see you this May at the PREMIER event for Infor LX & BPCS users! Join us for the conference and a special customer appreciation event!

Why attend?

  • Participate in exclusive training sessions
  • Attend user experience and industry presentations on topics relevant to your business
  • View new product demos to give you the tools needed to tackle issues we all share

Click here to register and please let us know that you will be attending!

What is the right balance of KPIs to make sure your production line is running at peak performance?

Analytics Dashboard

Crossroads RMC 0 33740 Article rating: 5.0

How can we make sure the production line is running at peak performance?

One very effective way is to put the right balance of production KPIs in place. Some of these are leading indicator KPIs that help provide insight into future performance and some are results KPIs that tell you how you have done. It is good to have both.

Check out this list of 21 examples of KPI indicators for 2020 to help improve manufacturing performance.

Analytics Dashboard for Infor LN & Baan
Analytics Dashboard for Infor LX, BPCS & Infor M3

First5354555658606162Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Considerations for Release to Warehousing for a Cost Item

When there are two Cost Items, one with Release to Warehousing applied and the other with Release to Warehousing not applied, upon approval of the Sales Order, the Cost Item that is released to Warehousing will go straight to Staged status, pending Shipment confirmation, while the Cost Item that is not released to Warehousing will be up for Sales Deliveries.

Apart from this main difference in functionality between having and not having this option to release to Warehousing checked, there are other impacts to consider. Below is some information gathered from various KBs related to the impact of having release to Warehousing applied (or not). KBs used as reference are listed as “– REF: KB XYZ”. Editing the checkbox “Release to Warehousing” itself If there is a Sales Order (in status Free is enough) for a Cost Item, the check box is not editable. As soon as all the Sales Orders for which the Item is involved are Closed (or Canceled or Deleted) the check box becomes editable again. – REF: KB 1439313 & KB 1613780 Simultaneous/separate release to Warehousing with Physical Items In a scenario where a Cost Item (that is released to Warehousing) and a physical Item are released to Warehousing separately, then the shipment confirmation of each of these Items will occur separately. If they are released simultaneously, the shipment of the Cost Item will not be processed unless and until the physical Item is ready to be shipped. – REF: KB 1449001 Note: Ensure a Warehouse is added to Order Lines to ensure Release to Warehousing Activity is applicable. – REF: KB 2229767 Invoicing

To invoice them separately or together, factors to consider are:

  • Composing Criteria, a list of fields that need to match to have a single invoice created – REF: KB 717977
  • Invoicing Methods (tcmcs0555m000) in the General tab, select Combine, for example, Shipments, to combine different Shipments of the same Sales Order into one Invoice. This Invoicing Method is also defined in
  • Invoice-to role of a Business Partner (tccom4112s000) in the Invoicing tab. – REF: KB 812637
  • For a Return Order where a Cost Item and a Physical Item were originally invoiced together, to invoice them together again, consider using Original Document type = Invoice and link the original Invoice to the Return Order. – REF: KB 2072847 

Note: Consider solution in KB 2108605 if Composing Criteria is met, yet still Credit Notes are not combined for a Return Sales Order copied from original Sales Order for one Physical Item and one Cost Item without release to Warehousing. 

ASN ASN cannot be generated for Purchase Order Lines with Cost Item if not released to Warehousing. – REF: KB 1548301 & KB 2111341 Intercompany Trade Intercompany Trade can be applied for a Cost Item that is released to Warehousing, as Intercompany Trade needs a Warehouse and a Department. – REF: KB 2112430 Customs Value Cost Items that are released to Warehousing that are handled via normal Sales Order Lines are considered as delivered goods and will get the customs value assigned like other Items being subject to warehouse handling. Cost Items handled on Shipment Lines as "Additional Cost" are not considered as delivered goods but as pure costs. The customs value of these shipment lines gets defaulted with a zero amount and cannot be modified. The same applies to additional costs on sales order lines. – REF: KB 1600847 Freight  Cost Items cannot be used for Freight handling. – REF: KB 1830170 Additional Cost

  • For automatically generated Additional Costs in Sales Orders, Cost Items that are released to Warehousing are not released to Warehousing. This is because automatic Additional Costs are always generated with 0 quantity, therefore only the amount is filled for these Lines, which leads to the Delivery Type being set to Sales and not Warehouse. As a result, delivery must take place in Sales module. – REF: KB 1995781
  • For Additional Cost Lines added to Shipment for Cost Items, refer to KB 2236856.

Intrastat Record When using Cost Items without release to Warehousing, there is no shipping data within Invoicing. Therefore, the corresponding Intrastat record cannot be found during the printing of the Invoice. To get the Invoice data filled on the Intrastat record, Cost Items with release to warehousing should be used. Otherwise, session Update Intrastat Transactions with Invoicing Data (tccom7271m100) should be ran to update the Invoicing data in Intrastat. – REF: KB 2005482

Previous Article Infor LN & Baan Tip: What conditions must exist before changing an item's inventory unit?
Next Article Infor LN & Baan Tip: Cash Flow Functionality and Setup
Print
53398 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories