Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 28280 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LN & Baan Finance Tip: How to clear balances on invoices that will be moved to a new company

Kathy Barthelt 0 65591 Article rating: 5.0

To clear out the balances of outstanding invoices that will be added into new companies or moved into new companies, credit notes could be created for them and have them linked to all the invoices of one customer/supplier. 

Another option is to...

Infor LN & Baan Tip: Did you know? PBOM – Effective Dates

Materials and Manufacturing

Kathy Barthelt 0 64168 Article rating: 5.0

Did you know? PBOM – Effective Dates

Some customers have noticed that when a PBOM is pushed from Engineering to Production, the effective date of the PBOM component lines does not match the effective date of the revision of the PBOM component.

Here is how it works:

Crossroads RMC's support team is friendly, well trained, experienced, and committed to resolving your support & technical issues as quickly & effectively as possible.

Crossroads RMC 0 24791 Article rating: 5.0

How good would you feel if you knew that 30+ years of ERP manufacturing experience was on the other end of the phone when you placed a support call?

That’s what our customers get when they call Crossroads RMC for help.

Crossroads RMC offers a number of services to help you make the most of your Infor ERP investment, regardless of the version of Infor LX, BPCS, Infor LN, Baan, or Infor M3, you are running. Our support team is friendly, well trained, experienced, and committed to resolving your support and technical issues as quickly and effectively as possible. To ensure all your support needs are met, we offer several different methods:

  • TELEPHONE SUPPORT:
    Our phones are answered by live representatives to ensure that you receive prompt, personal, and efficient assistance. These services are available Monday through Friday 8:30 am to 5:00 pm ET. We also offer standby support and after-hour support when requested.
  • ONLINE SUPPORT:
    Online support is available by logging onto your system using a remote connection. With a live connection, our consultants are able to view your system and troubleshoot issues in real-time.
  • REMOTE & ON-SITE CONSULTING:
    Consulting is an excellent option if more in-depth service, training, or troubleshooting is needed. End-User training or group custom training on new features and solutions is also handled effectively using this method of support.
  • BUSINESS ASSESSMENTS:
    Experienced Crossroads RMC Consultants will compare your existing business processes with your existing software and put together a detailed report of their findings. This includes recommendations for improving the day-to-day running of your business while getting the maximum benefit from your software. This also ensures that you are up to date with any features and technologies without adding disruption to your business.

Learn more about our support services>

Infor LN & Baan Tip: Performance Standard Cost

by Infor

Kathy Barthelt 0 63993 Article rating: 5.0

Everything you ever wanted to know about Calculating Standard Cost and Actualizing Standard Cost / Revaluing Inventory (ticpr2210m000 | ticpr2220m000)

Calculating standard cost and re-valuing inventory are important capabilities within your Infor ERP system for a variety of reasons. Sometimes these sessions experience performance issues. Here is a brand new PowerPoint released by Infor to discuss both the functional and technical side of these sessions. Get every last what, where, why, and how answered so that you can improve how these sessions run on your system.

Download Infor PowerPoint>

First3940414244464748Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Project Status Options

Ever wonder what the implications are of choosing one project status versus another?

Here is the explanation of project status possible values:

Free
You can carry out project engineering. This means that you can:

  • Define the project master schedule (PMS) by using the Project Control module.
  • Maintain the project structure.
  • Maintain the customized product structure by using customized bills of material and routing sheets.
  • Carry out project estimating.

Simulated
You simulate the rough capacity requirements planning and the detailed material and resource requirements planning (RRP) based on the network planning. The capacity requirements for a simulated project are visualized separately. Infor LN (ERP LN) generates planned RRP purchase orders, planned production orders, and PRP warehouse orders for customized items. However, those orders cannot be released. Moreover, the RRP does not allocate standard items to the project.

Active
This status indicates the project's execution stage. You can release planned orders so that the required purchase and production activities can be actually started and completed.

Canceled
The project has been canceled. You cannot release new orders for the project, but you can, however, finish pending logistical activities. You can close a canceled project, but a project can also remain canceled. If the project remains canceled, be aware that the final costs are not posted to Financials, and that WIP can still exist for completed orders. Costs are only posted if you close the project.

Finished
As far as manufacturing is concerned, the project is finished. Also, all purchase and production activities have been completed or closed, and all sales orders have been delivered for the project.

Closed
Financially, the project has been closed. This means that the financial project results have been computed. Financial project transactions can no longer be posted to the project.

To be Closed
If you select the COGS and Revenues restricted to Financial Company of PCS Project check box in the Project Control Parameters (tipcs0100m000) session, financial transactions are posted on the financial companies of the sales office, service department, and/or warehouse instead of on the financial company of the PCS project. If internal invoices are sent from the PCS project to those departments, and the internal invoices are not completed yet, the Close Project (tipcs2250m000) session sets the project status to To be Closed instead of to Closed. You must first complete the internal invoices, and then run the Close Project (tipcs2250m000) session again to set the project status to Closed.

Archived
The project has been archived. This means that all project data has been stored in archive files and is removed from the original files.

Previous Article Infor LN & Baan Tip: LN Order Management - Generating Purchase Receipts
Next Article Infor LN & Baan Tip: Cost Component Setup
Print
57012 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories