Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)

Kathy Barthelt 0 66878 Article rating: 5.0

When the Generate Order Planning (cprrp1210m000) session is run it can take minutes to days to finish the process.

The performance of this session depends on many settings, like the number of plan items, the number of orders, but it also depends on hardware and database setup.

Here are some guidelines on how performance can be improved...

Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

George Moroses 0 26805 Article rating: 5.0

This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply....

Infor LX & BPCS Materials Tip: Over-Receipts

George Moroses 0 28893 Article rating: 5.0

If Infor LX is set up to prevent over-receipts, you cannot post a receipt quantity that is more than the remaining PO line quantity with the over-tolerance % added to it.

As an alternative, you can:

  • Receive the maximum, remaining line quantity plus over-tolerance percentage quantity, and reject the balance to quarantine or
  • Receive the full quantity into quarantine.


Note: Over-receipt checking applies only to receipts to stock.

Infor LN & Baan Tip of the Week: Limitations of Customer Defined Fields (CDFs)

Kathy Barthelt 0 70765 Article rating: 5.0

Customer Defined fields are fields that can be added to tables, screens, reports, and BODs. Validation and calculation logic can be defined around those fields. This gives you great added capability and flexibility… however, are you aware of the limitations of using CDFs?

  • You cannot define customer-defined fields for tables within Tools (the tl and tt packages).
  • External integrations.....

Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX

George Moroses 0 27118 Article rating: 5.0

The Credit Card Data Area program, SYS045D, enables you to create and maintain a configuration file that provides a gateway to a third-party payment application. The information you set up with this program is required to allow Infor LX to communicate with the credit card processing application that passes credit card payment information between Infor LX and the credit card providers.

Access: SYS menu

  • Use the Credit Card Data Area screen, SYS045D-01, to...

Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 28006 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

First3738394042444546Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

Optimize Your Manufacturing Today!

Previous Article BPCS/LX Tip of the Week: Role-Based Security
Next Article BPCS/LX Tip of the Week: Inventory Transaction Post to G/L by Cost Type
Print
28553 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.